Run Through the Base, Not To the Base
Thankfully, baseball season is back. While listening to a broadcast of my favorite team yesterday, I heard the announcer repeat the fundamental lesson of “running through the base, not to the base.” Running to a base leaves the runner no option or momentum to continue. When running through the base, the runner has the option to stop or keep going to the next base. This too is an important lesson for government contractors – run through your goals to preserve your options.
Recently, a contractor’s appeal was dismissed when the ASBCA found it had no jurisdiction because the contractor did not first submit a claim to the contracting officer. In the contractor’s defense, he probably (and understandably) thought a claim wasn’t necessary when a settlement had already been reached between the contractor and the Army, as evidenced by a written agreement from the contracting officer.
However, “through bureaucratic indifference, the government failed to keep its promise to pay appellant, failed to explain why it was not paying, and failed to retain records that demonstrate what happened.” ASBCA No. 60597, decided March 3, 2017 (underlining added). The Board was “sympathetic” to the contractor’s “predicament,” but the absence of a certified claim meant the Board was powerless to do anything.
To keep your options open and maintain momentum, claims may be necessary even when they shouldn’t be.
Roads & Bridges | Award Upheld in W. Va. Caisson Dispute
AWARD UPHELD IN W.VA. CAISSON DISPUTE
Federal court reinforces high bar for overturning arbitration
In 2018, the West Virginia Department of Highways (DOH) awarded […]
Roads & Bridges |Let the Contract Lead
LET THE CONTRACT LEAD
Documents offer guidance needed to manage risk without derailing projects
Construction is an industry of managed risk. Whether the prices […]
Roads & Bridges | When is an Invoice Really an Invoice?
WHEN IS AN INVOICE REALLY AN INVOICE?
All court decisions are opinions. Appellate court decisions are typically made by a panel of three […]
Roads & Bridges | Clarifying Punitive Damages
CLARIFYING PUNITIVE DAMAGES
In June 2021, the South Dakota Department of Transportation contracted for the demolition and construction of a bridge on State […]
Roads & Bridges | When Approximate Means Assumed Risk
WHEN APPROXIMATE MEANS ASSUMED RISK
A New York Court Shows How Performance Specifications Can Leave Contractors Holding the Bag
Sometimes when we are told […]
Roads & Bridges | From Roman Arches to AI
FROM ROMAN ARCHES TO AI
Can Construction Evolve Without Risk?
The construction industry blends old with new. From ancient Roman archways and aqueducts and […]
Roads & Bridges | Caught in the Middle
CAUGHT IN THE MIDDLE
New Mexico bridge case highlights the importance of written agreements for changes and delay compensation
In construction contracting, hope for […]
Roads & Bridges | Wait and It’s Waived
WAIT AND IT’S WAIVED
Roads & Bridges | Supreme Court Ruling on Arbitration Delay
Don’t wait to arbitrate! Progressing too far down the litigation […]
Roads & Bridges | Court Defines When Contractors Can Withdraw Due to Mistakes
BIDDING BLUNDER
Roads & Bridges | Court Defines When Contractors Can Withdraw Due to Mistakes
For over 125 years, the vast majority of jurisdictions […]










