This applies to general contractors, subcontractors, and suppliers. Each can be the party preparing and transmitting a form of purchase order or (sub)contract or the party receiving the form and obligated to respond timely with agreement/performance or disagreement.
This happens every single day when a typical negotiation begins with a proposal, estimate, or bid from one party to the other. Next, an oral or informal written discussion occurs between the parties and terms are orally or informally agreed. At this point, the proposal, estimate, or bid may be marked-up. But, the negotiation is often not over and the agreement is not yet final.
After the proposal is marked-up, one party transmits a written P.O. or (sub)contract to the other. The proposal terms are not identical to the P.O. terms or (sub)contract. Among businesses, the receiving party must review and respond within ten (10) days. Failure by the receiving party to respond or commencing performance generally obligates the receiving party to the P.O. or (sub)contract terms.
The point is: review what you receive and make sure you agree or notify the other party that you disagree before beginning performance. Otherwise, you are probably bound to the terms of the other party’s form, which you did not write or prepare and which are probably not in your favor.
In the case of U.S. f/u/b/o San Benito Supply v. KISAQ-RQ 8A 2 JV, (U.S. Dist. Ct., N.D. California, Jan. 28, 2015), the lower-tier supplier was bound to the subcontractor’s purchase order when the supplier failed to disagree. In that case, the supplier was obligated to provide a mix design for 6000 psi concrete for a USACOE project at Fort Hunter Liggett in California.
The supplier’s proposal included the statement, “Quality Assurance program by others.” By this statement, the supplier argued the subcontractor was obligated to ensure the mix design was adequate. (The specifications were for performance, not design.) However, the subcontractor’s purchase order (the later document in the negotiation) included no such language. Although the supplier never signed and returned the subcontractor’s purchase order, the supplier did not inform the subcontractor of its disagreement instead commencing performance.
What began as the supplier’s Miller Act Claim for non-payment ended with the supplier paying for its defective concrete mix design, which was discovered after placement.
Roads & Bridges
Where Does the Buck Stop?
Jon is a monthly contributor to Roads & Bridges magazine. He has been writing the law section for the magazine since January 2020. The link below will take you directly to the Roads & Bridges […]
Pay-If-Paid Unenforceable in Virginia Starting Jan. 1, 2023
As of Jan. 1, 2023, pay-if-paid clauses are unenforceable, regardless of whether a surety/payment bond claim is involved. This is only for subcontracts created on/after 1/1/23.
Also for subcontracts created on/after 1/1/23, the prime must specifically […]
How Short is Too Short
A limitations period is too short when it’s unreasonably short.
Construction Contracting Without Relief Clauses During COVID-19
What to do if your contract lacks the parts to handle COVID-19? Considerations for creating new contracts during COVID-19.
Your Contract Can Handle COVID-19
Uncertainty and risk are not new or novel to contractors. Contracts reduce uncertainty and share the risk of doing or providing something. COVID-19 may have contributed to, but it has not single-handedly created, uncertainty and risk.
Contractors Can Use RFI to Notify the Government
The Board (and the government) should not elevate form over substance in evaluating the sufficiency of a contractor’s notice.
Taxes Due!
It’s tax season again, so it’s time to pay the piper.
Contractor Wins when Government Reconsiders Accord
Ever had buyer’s remorse or second-guessed a decision? When the U.S. Army Corps of Engineers did that, a Contractor won its claim for time and money.
On a flood control project near Nogales, Arizona, severe flooding […]
Claim Certified with Digital Signature Deemed OK
The law is not a trend-setter. It doesn’t readily change or adapt to tech. So, a commonplace practice in business became a dispute when a claimant digitally certified a claim under the Contract Disputes Act.

Jonathan J. Straw
Blog Author
Contact Jonathan
Partner | KraftsonCaudle.com
Download Jon’s Bio
