You told the guy to do the work, the work is done, and now it’s time for payment, right? But, you only told the guy to do the work because somebody else told you do the work and that somebody else now won’t pay. This is, perhaps, the most frequent problem in construction.
Here is the short story of an Owner, GC, and Sub on a public building project in Virginia. During the project, changes were made (imagine that on a construction project). The Sub completed the changes and its scope of work three months later than planned. The Sub submitted Change Requests to the Owner through the GC. The Owner denied the Sub’s Change Requests and did not pay the GC for the delays and changed work. In turn, the GC did not pay the Sub because the Owner did not pay the GC. The Sub sued the GC and lost because of valid pay-when-paid and pay-if-paid provisions in the subcontract.
In reading the court’s opinion (Young Electrical Contractors, Inc. v. Dustin Construction, Inc., Md. App. No. 266 (Dec. 28, 2016)), there are three lessons for general contractors:
- Ask Owners. You’ll have a better chance of enforcing a pay-when-paid or pay-if-paid subcontract provision when you submit subcontractors’ change requests to owners. It’s impossible to say that the owner said NO when the general contractor fails to ask. If you don’t submit a sub’s change requests to the owner, you (the general contractor) may bear the risk.
- Get Paid to Pay. Many words are wasted over whether a clause is a pay-when-paid vs. pay-if-paid provision. Yes, there is a distinction and it can make a difference. But, it’s generally enough to remember that under either clause, the owner will or must pay the general before the general will or must pay the subcontractor.
- Repeat Specifically. You’ll benefit from specific and repeated pay-when-paid or pay-if-paid provisions vs. a blanket or general provision. Insert conditional language (g., “if”) at each of three typical subcontract payment scenarios, including, payment for: (1) undisputed work, (2) disputed (i.e., changed) work, and (3) claims and disputes.
Roads & Bridges
Where Does the Buck Stop?
Jon is a monthly contributor to Roads & Bridges magazine. He has been writing the law section for the magazine since January 2020. The link below will take you directly to the Roads & Bridges […]
Pay-If-Paid Unenforceable in Virginia Starting Jan. 1, 2023
As of Jan. 1, 2023, pay-if-paid clauses are unenforceable, regardless of whether a surety/payment bond claim is involved. This is only for subcontracts created on/after 1/1/23.
Also for subcontracts created on/after 1/1/23, the prime must specifically […]
How Short is Too Short
A limitations period is too short when it’s unreasonably short.
Construction Contracting Without Relief Clauses During COVID-19
What to do if your contract lacks the parts to handle COVID-19? Considerations for creating new contracts during COVID-19.
Your Contract Can Handle COVID-19
Uncertainty and risk are not new or novel to contractors. Contracts reduce uncertainty and share the risk of doing or providing something. COVID-19 may have contributed to, but it has not single-handedly created, uncertainty and risk.
Contractors Can Use RFI to Notify the Government
The Board (and the government) should not elevate form over substance in evaluating the sufficiency of a contractor’s notice.
Taxes Due!
It’s tax season again, so it’s time to pay the piper.
Contractor Wins when Government Reconsiders Accord
Ever had buyer’s remorse or second-guessed a decision? When the U.S. Army Corps of Engineers did that, a Contractor won its claim for time and money.
On a flood control project near Nogales, Arizona, severe flooding […]
Claim Certified with Digital Signature Deemed OK
The law is not a trend-setter. It doesn’t readily change or adapt to tech. So, a commonplace practice in business became a dispute when a claimant digitally certified a claim under the Contract Disputes Act.

Jonathan J. Straw
Blog Author
Contact Jonathan
Partner | KraftsonCaudle.com
Download Jon’s Bio
