We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
The prime contractor described below recovered its costs by properly not assuming a duty. This required a distinction among duties that:
- must be done;
- should be done; or
- need not be done.
On a project for the Florida Department of Transportation, the Prime Contractor terminated its landscaping subcontractor for default after the obligatory 72-hour cure period passed. The Prime then promptly submitted a performance bond claim to the terminated sub’s surety. The Prime was obligated to and did wait the 15-day “grace period” for the surety to investigate and respond. However, when the surety failed to substantively respond, the Prime properly mitigated its damages by engaging a replacement subcontractor.
Upon completion of the replacement subcontractor’s work, the Prime submitted its recoverable costs to the defaulted sub’s surety. The surety denied payment by arguing the Prime failed to assist with the surety’s investigation of the default. The Court awarded summary judgment to the Prime finding it had no duty to assist with the surety’s investigation absent an express requirement, which was not included in the bond or subcontract.
The Court agreed that the Prime need not help the surety with the heavy lifting of investigating the sub’s termination for default.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]
One-Sided Construction Arbitration Clause Valid in Virginia
When it’s time to butt heads, know how the local turf (court) will interpret the clause.
Manage the Risk of Construction Changes
Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes). As in life, embrace and manage the change don’t run from it.
Want Your Profit? Prove a Constructive Change, Not a Suspension of Work.
What’s the Difference Between a Suspension of Work and a Constructive Change? For federal contractors, there are two main differences: . . .
No Special Defenses to Arbitration Agreements
Arbitration agreements, whether they are separate or part of a larger agreement, are contracts – an enforceable set of promises between parties. […]
How to Find (and Confirm) the Plain Meaning in a Contract
Contract formation confirms the parties understand and agree to all the essential terms. When that understanding and agreement fades, how do you […]
Navigating the Requirements for Claims against Virginia Public Entities
Contractors making claims against Virginia public entities must follow ALL applicable requirements. Such requirements may be found in several places, so check […]
Virginia General Contractors Not Protected from Pre-Work Claim Waivers
On March 2, 2018, the Governor approved an act of the Virginia General Assembly to make unenforceable pre-work waivers of lien rights […]