What’s the difference between a suspension of work and a constructive change? For federal contractors, there are two important differences:

  1. If you want profit, prove a constructive change.
  2. If any other contract clause affords an equitable adjustment (e.g., Changes Clause), the Suspension of Work clause won’t help you.

To recover from a suspension of work, a contractor must show:

  1. Contract performance was delayed;
  2. Government directly caused the delay;
  3. The delay was for an unreasonable period of time; and
  4. The contractor suffered damages therefrom (excluding profit); and
  5. No other clause provides an equitable adjustment to the Contractor

FAR § 52.242-14

To prove a constructive change, a contractor must show:

  1. Any written or oral order from the Contracting Officer;
  2. Not a directed change;
  3. That caused a change;
  4. Contractor gave timely notice that it considered the order as a change; and
  5. The contractor suffered damages therefrom.

FAR § 52.243-4(b)

In a recent Civilian Board of Contract Appeals decision, the Board agreed with the contractor in finding an unreasonable delay (179 days) and awarded damages for a suspension of the work.  In the same decision, the Board also found a constructive change in the contractor’s favor.  The Board did not discuss why the suspension of work clause prevailed when the contractor may have been able to show a constructive change (unless, perhaps, notice of a constructive change was inadequate).

BCPeabody Construction Services, Inc. v. Dept. of Veterans Affairs, CBCA No. 5410, March 26, 2018

Published On: April 25, 2018

Share This Story, Choose Your Platform!

Are We There Yet?

May 8, 2017|

Next time you close a deal, get the essential terms on paper and signed by all parties before it’s Miller Time.

Show Me the Money!

May 1, 2017|

You told the guy to do the work, the work is done, and now it’s time for payment, right?  But, you only told […]

Reasonable ≠ Ratio

April 24, 2017|

“Circuit court litigation comes at a price, sometimes a heavy price.”

Words Matter

April 17, 2017|

Remember the adage, “what you say today could bite you tomorrow.”

Recently, a Contractor won its argument before the Armed Services Board of […]

Speak Now or Pay Later

June 5, 2015|

This applies to general contractors, subcontractors, and suppliers.  Each can be the party preparing and transmitting a form of purchase order or […]

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!