What’s the difference between a suspension of work and a constructive change? For federal contractors, there are two important differences:
- If you want profit, prove a constructive change.
- If any other contract clause affords an equitable adjustment (e.g., Changes Clause), the Suspension of Work clause won’t help you.
To recover from a suspension of work, a contractor must show:
- Contract performance was delayed;
- Government directly caused the delay;
- The delay was for an unreasonable period of time; and
- The contractor suffered damages therefrom (excluding profit); and
- No other clause provides an equitable adjustment to the Contractor
To prove a constructive change, a contractor must show:
- Any written or oral order from the Contracting Officer;
- Not a directed change;
- That caused a change;
- Contractor gave timely notice that it considered the order as a change; and
- The contractor suffered damages therefrom.
In a recent Civilian Board of Contract Appeals decision, the Board agreed with the contractor in finding an unreasonable delay (179 days) and awarded damages for a suspension of the work. In the same decision, the Board also found a constructive change in the contractor’s favor. The Board did not discuss why the suspension of work clause prevailed when the contractor may have been able to show a constructive change (unless, perhaps, notice of a constructive change was inadequate).
BCPeabody Construction Services, Inc. v. Dept. of Veterans Affairs, CBCA No. 5410, March 26, 2018
Are We There Yet?
Next time you close a deal, get the essential terms on paper and signed by all parties before it’s Miller Time.
Show Me the Money!
You told the guy to do the work, the work is done, and now it’s time for payment, right? But, you only told […]
Reasonable ≠ Ratio
“Circuit court litigation comes at a price, sometimes a heavy price.”
Words Matter
Remember the adage, “what you say today could bite you tomorrow.”
Recently, a Contractor won its argument before the Armed Services Board of […]
Run Through the Base, Not To the Base
Run Through the Base, Not To the Base
Thankfully, baseball season is back. While listening to a broadcast of my favorite team yesterday, […]
Having Your Cake and Eating It Too: Attorneys Fees Without a Contract Clause
How often have you wanted to take a dispute “to the mattresses” (think, The Godfather), but the cost was prohibitive? You have […]
Choose Your Own Venue: Where to File a Miller Act Lawsuit
Do you remember the Choose Your Own Adventure books? If you are a subcontractor on a federal project, where should you […]
Speak Now or Pay Later
This applies to general contractors, subcontractors, and suppliers. Each can be the party preparing and transmitting a form of purchase order or […]
General Contractors Waive Goodbye
General Contractors: When was the last time a private owner asked you to waive your lien rights before you did any work? […]