As if you needed confirmation that the Federal Miller Act is a powerful tool for unpaid subcontractors, this is it. Even when a Prime ordered and accepted the Sub’s work, but didn’t have to pay under the Subcontract, the Subcontractor still got paid by the Prime’s Surety.
On a project for the U.S. Army Corps of Engineers in Qatar, a Subcontractor agreed to provide labor and materials for telecommunication systems. The Prime ordered and accepted a portion of the work and the Sub performed. The Corps then terminated the Prime for default, so the Prime refused to pay the Sub.
The Prime breached the Subcontract but because of its termination by the Corps and terms of the Subcontract, the Prime was not on the hook for any damages to the Sub. Notably, the Court stated that, if “the Court were to base its decision on whether a party had acted unprofessionally towards another party, had mislead another party (whether intentionally or not), or had wrongly accused another party of failing to perform under a contract, then the court would find the [Prime should pay the Sub].” But, the Court’s jurisdiction is limited to interpreting and applying only the applicable law, including the parties’ agreement.
However, under the Federal Miller Act, the Prime’s Surety was liable for the full amount of damages. The Surety’s liability is independent of its Principal’s liability and required only a showing that the Sub had performed the work and had not been paid.
Pragmatically, the Surety will pay the Sub and then demand reimbursement from its Principal, the Prime.
U.S. f/u/b/o VT Milcom, Inc. v. PAT USA, Inc., Case No. 5:16-cv-00007, (W.D. Va., July 14, 2017).
One-Sided Construction Arbitration Clause Valid in Virginia
When it’s time to butt heads, know how the local turf (court) will interpret the clause.
Manage the Risk of Construction Changes
Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes). As in life, embrace and manage the change don’t run from it.
Want Your Profit? Prove a Constructive Change, Not a Suspension of Work.
What’s the Difference Between a Suspension of Work and a Constructive Change? For federal contractors, there are two main differences: . . .
No Special Defenses to Arbitration Agreements
Arbitration agreements, whether they are separate or part of a larger agreement, are contracts – an enforceable set of promises between parties. […]
How to Find (and Confirm) the Plain Meaning in a Contract
Contract formation confirms the parties understand and agree to all the essential terms. When that understanding and agreement fades, how do you […]
Navigating the Requirements for Claims against Virginia Public Entities
Contractors making claims against Virginia public entities must follow ALL applicable requirements. Such requirements may be found in several places, so check […]
Virginia General Contractors Not Protected from Pre-Work Claim Waivers
On March 2, 2018, the Governor approved an act of the Virginia General Assembly to make unenforceable pre-work waivers of lien rights […]
Adding Terms to a Government Contract without Saying So
Imagine an incredulous Contractor asking, “Show me in the Contract where it says I’m supposed to do X?” The Government Contracting Officer smugly answers, “even though the Contract doesn’t say so, you must do it anyway.” Is that even possible, when, how?
Differing Site Conditions: When the Part Does Not Equal the Whole
If all apples are fruit, then why are all fruit not apples?