Recently, I posted about the Spearin Doctrine, which says that if a contractor follows the owner’s plans and specifications and something doesn’t work, the contractor is generally not at fault. But, this only works if the contractor first follows the owner’s design. It doesn’t work when the owner’s design will work as is, but you think it could be better.
In recently denying an HVAC Contractor’s appeal, the Armed Services Board of Contract Appeals stated, “the government may require performance [either] in excess of, or below, the standard normally accepted in a trade.” In other words, the government need not follow the industry standard. It can do less or more.
Under a firm, fixed-price contract managed by the Army Corps of Engineers, the Contractor agreed to upgrade the HVAC equipment at a Child Development Center at a facility in Hanover, NH. The project was “limited by budget constraints,” but included work intended to remedy the “thermal discomfort” of the facility’s occupants.
The Contractor advised the Corps that certain design improvements would help the end-user. The Corps considered the advice, but rejected the Contractor’s suggestion. Thereafter, the Contractor “delayed the project because it disagreed with the government’s design choices.” Ultimately, the Corps terminated the Contractor for default.
Navigating the Requirements for Claims against Virginia Public Entities
Contractors making claims against Virginia public entities must follow ALL applicable requirements. Such requirements may be found in several places, so check […]
Virginia General Contractors Not Protected from Pre-Work Claim Waivers
On March 2, 2018, the Governor approved an act of the Virginia General Assembly to make unenforceable pre-work waivers of lien rights […]
Adding Terms to a Government Contract without Saying So
Imagine an incredulous Contractor asking, “Show me in the Contract where it says I’m supposed to do X?” The Government Contracting Officer smugly answers, “even though the Contract doesn’t say so, you must do it anyway.” Is that even possible, when, how?
Differing Site Conditions: When the Part Does Not Equal the Whole
If all apples are fruit, then why are all fruit not apples?
Forum Selection Can Be a Home-Court Advantage
I promise that any disputes between us will be argued at your house. Time passes and a dispute begins to brew. Now, I want to argue at my house, not at yours. You pay costs to argue at my house that you wouldn’t have incurred had I done as agreed. Should I have to reimburse your costs?
No-Damage-for-Delay and Owner-Related Dispute Clauses are No Defense to Surety Liability Under Miller Act
Prime Government Contractors - you may need to update your interim payment waivers.
Contractual Fairness is Whatever the Parties’ Agreed
When you know a current action or inaction is wrong, but you do not object, should you be allowed to object later?
Which Comes First – Specifications or Drawings?
Sometimes it's not better to ask for forgiveness after-the-fact.
Government Contract Claims: When Appeal is Rejection of Settlement
Without a reservation of rights, appealing a Contracting Officer’s Final Decision is a rejection of any offer of payment or settlement included therein. So, the contractor had only three options.










