Have you ever played hide and seek? If you are the seeker, do you win the game when you find the hidden person? Yes, of course!
Unless, you’re a government contractor seeking “hidden” requirements that seem to pop-up around every corner. Just when it seems you’ve found the answer, requirement, specification, or drawing detail, the government replies that you missed something and should have kept seeking.
Do not fear, you may yet win this round. Give notice, track your costs, and organize the documents supporting your position. Later you may submit a claim.
Under a recent design-build project for the U.S. Navy, the contractor submitted claims for extra work on the construction of a dormitory at Aviano Air Base in Italy. Although the ASBCA denied the appeal because the contractor didn’t consider the many requirements that were incorporated into the contract by reference (not verbatim), the case provides a good lesson for contractor’s –
When it seems you’ve found the answer, keep looking to ensure the answer doesn’t change.
Appeals of A.T.I. Tacose S.C.a R.L., ASBCA Nos. 59157 and 59200 (Jan. 4, 2017).
Termination for Convenience was OK to Get a Lower Price
When Massachusetts’ highest State court rejected Federal law on termination for convenience (T4C) a public entity’s “sole discretion . . . for […]
Pirates (Parties) Should Arbitrate Arbitrability
Yes, the word “pirates” is an anagram for “parties.” Participants in a lawsuit, arbitration, or mediation are collectively referred to as parties. Are they pirates too?
Very Bad Behavior Without Bad Faith is Not a Breach of Contract
Despite “abhorrent” behavior by the Army Corps of Engineers, a majority of the Armed Services Board of Contract Appeals held there was […]
Government Construction Contracts Require Bonds, Even When Contract Doesn’t Say So
Yesterday (Nov. 5, 2018), the Fed. Cir. Ct. of Appeals again endorsed the Christian doctrine, which can make unstated requirements part of a government contract.
Government’s Negligent Estimate a Trick?
The Government’s negligent estimate failed to provide the “most current information available.”
Prime Contractor Had No Duty to Help Surety Investigate Sub’s Default
We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]