You told the guy to do the work, the work is done, and now it’s time for payment, right? But, you only told the guy to do the work because somebody else told you do the work and that somebody else now won’t pay. This is, perhaps, the most frequent problem in construction.
Here is the short story of an Owner, GC, and Sub on a public building project in Virginia. During the project, changes were made (imagine that on a construction project). The Sub completed the changes and its scope of work three months later than planned. The Sub submitted Change Requests to the Owner through the GC. The Owner denied the Sub’s Change Requests and did not pay the GC for the delays and changed work. In turn, the GC did not pay the Sub because the Owner did not pay the GC. The Sub sued the GC and lost because of valid pay-when-paid and pay-if-paid provisions in the subcontract.
In reading the court’s opinion (Young Electrical Contractors, Inc. v. Dustin Construction, Inc., Md. App. No. 266 (Dec. 28, 2016)), there are three lessons for general contractors:
- Ask Owners. You’ll have a better chance of enforcing a pay-when-paid or pay-if-paid subcontract provision when you submit subcontractors’ change requests to owners. It’s impossible to say that the owner said NO when the general contractor fails to ask. If you don’t submit a sub’s change requests to the owner, you (the general contractor) may bear the risk.
- Get Paid to Pay. Many words are wasted over whether a clause is a pay-when-paid vs. pay-if-paid provision. Yes, there is a distinction and it can make a difference. But, it’s generally enough to remember that under either clause, the owner will or must pay the general before the general will or must pay the subcontractor.
- Repeat Specifically. You’ll benefit from specific and repeated pay-when-paid or pay-if-paid provisions vs. a blanket or general provision. Insert conditional language (g., “if”) at each of three typical subcontract payment scenarios, including, payment for: (1) undisputed work, (2) disputed (i.e., changed) work, and (3) claims and disputes.
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]
One-Sided Construction Arbitration Clause Valid in Virginia
When it’s time to butt heads, know how the local turf (court) will interpret the clause.
Manage the Risk of Construction Changes
Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes). As in life, embrace and manage the change don’t run from it.
Want Your Profit? Prove a Constructive Change, Not a Suspension of Work.
What’s the Difference Between a Suspension of Work and a Constructive Change? For federal contractors, there are two main differences: . . .
No Special Defenses to Arbitration Agreements
Arbitration agreements, whether they are separate or part of a larger agreement, are contracts – an enforceable set of promises between parties. […]
How to Find (and Confirm) the Plain Meaning in a Contract
Contract formation confirms the parties understand and agree to all the essential terms. When that understanding and agreement fades, how do you […]
Navigating the Requirements for Claims against Virginia Public Entities
Contractors making claims against Virginia public entities must follow ALL applicable requirements. Such requirements may be found in several places, so check […]
Virginia General Contractors Not Protected from Pre-Work Claim Waivers
On March 2, 2018, the Governor approved an act of the Virginia General Assembly to make unenforceable pre-work waivers of lien rights […]
Adding Terms to a Government Contract without Saying So
Imagine an incredulous Contractor asking, “Show me in the Contract where it says I’m supposed to do X?” The Government Contracting Officer smugly answers, “even though the Contract doesn’t say so, you must do it anyway.” Is that even possible, when, how?