“Circuit court litigation comes at a price, sometimes a heavy price.”
Does your contract include an attorneys fees provision? Does it include words like “reasonable” or “prevailing party?” If so, then the prevailing party may be reimbursed for its “reasonable” attorneys fees expended in the litigation or arbitration process.
On April 13, 2017, the Virginia Supreme Court held the trial court of the City of Virginia Beach abused its discretion when the plaintiff recovered the entire amount it sought from the defendant ($500), but defendant only had to pay $375 out of the $9,568.50 total attorneys fees expended to reach the judgment.
Under Virginia law, a Court or tribunal (e.g., arbitrator or arbitration panel) will typically consider at least seven different factors to determine how much is “reasonable.” Determining a reasonable amount is not a simple ratio calculation nor can it be predicted with certainty. The Court stated “merely applying a ratio between the damages actually awarded and damages originally sought will not satisfy the reasonableness inquiry.”
The Court also cautioned that parties should be careful not to overinflate their damages as “an unreasonably exaggerated claim for damages provokes a proportional response.” “This unnecessarily inflates the costs of litigation for both sides and increases the possibility that one will end up liable to the other for an exorbitant award of attorney’s fees.”
Lambert v. Sea Oats Condominium Association, Inc., Record No. 160269 (April 13, 2017).
It’s Good to Be the King
Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.” It’s also true when asserting claims against the State or an arm or agent of the State.
Smoke Without Fire: Damage from Concrete Dust Covered by Insurance
You’ve heard, “where there’s smoke, there’s fire.” In this instance, the smoke was concrete dust that damaged a warehouse full of aircraft […]
Changes Made After Substantial Completion Did Not Extend Overall Project Time
Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess […]
One-Sided Construction Arbitration Clause Valid in Virginia
When it’s time to butt heads, know how the local turf (court) will interpret the clause.
Manage the Risk of Construction Changes
Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes). As in life, embrace and manage the change don’t run from it.
Want Your Profit? Prove a Constructive Change, Not a Suspension of Work.
What’s the Difference Between a Suspension of Work and a Constructive Change? For federal contractors, there are two main differences: . . .
No Special Defenses to Arbitration Agreements
Arbitration agreements, whether they are separate or part of a larger agreement, are contracts – an enforceable set of promises between parties. […]
How to Find (and Confirm) the Plain Meaning in a Contract
Contract formation confirms the parties understand and agree to all the essential terms. When that understanding and agreement fades, how do you […]
Navigating the Requirements for Claims against Virginia Public Entities
Contractors making claims against Virginia public entities must follow ALL applicable requirements. Such requirements may be found in several places, so check […]