The White House has directed Agency heads to “terminate or modify . . . covered contracts.” With some exceptions, there are numerous potential contracts on the chopping block. What should contractors do?
Upon receipt of a unilateral modification, assess whether the cost or time will increase in unchanged areas. For example, deductive changes for certain work could increase costs for other work that must still be performed. If costs were increased because of deductive changes, then carefully consider submitting a request for equitable adjustment.
Upon receipt of a notice of complete termination for convenience, promptly stop incurring further costs and, within one year of the termination, present a reasonable and well-supported termination settlement proposal to the Government under FAR 52.249-2(e). Recoverable costs include:
1. Costs actually incurred;
2. Profit on the work actually done; and
3. Costs of preparing a termination settlement proposal.
Upon receipt of a notice of partial termination for convenience, promptly stop incurring costs related to the terminated portion of the work and present a request for equitable adjustment within 90 days of the notice under FAR 52.249-2(l).
HEADER PHOTO: Termination by Nick Youngson CC BY-SA 3.0 Alpha Stock Images
Roads & Bridges | Reshaping Agreements
RESHAPING AGREEMENTS | Oral Agreements Must Be Written in Stone
Reuse, reshaping, and/or reapplication of existing materials was the goal in this roadway […]
Pay-If-Paid Unenforceable in Virginia Starting Jan. 1, 2023
As of Jan. 1, 2023, pay-if-paid clauses are unenforceable, regardless of whether a surety/payment bond claim is involved. This is only for […]
How Short is Too Short
A limitations period is too short when it’s unreasonably short.
Construction Contracting Without Relief Clauses During COVID-19
What to do if your contract lacks the parts to handle COVID-19? Considerations for creating new contracts during COVID-19.
Your Contract Can Handle COVID-19
Uncertainty and risk are not new or novel to contractors. Contracts reduce uncertainty and share the risk of doing or providing something. COVID-19 may have contributed to, but it has not single-handedly created, uncertainty and risk.
Contractors Can Use RFI to Notify the Government
The Board (and the government) should not elevate form over substance in evaluating the sufficiency of a contractor’s notice.
Taxes Due!
It’s tax season again, so it’s time to pay the piper.
Contractor Wins when Government Reconsiders Accord
Ever had buyer’s remorse or second-guessed a decision? When the U.S. Army Corps of Engineers did that, a Contractor won its claim […]
Claim Certified with Digital Signature Deemed OK
The law is not a trend-setter. It doesn’t readily change or adapt to tech. So, a commonplace practice in business became a dispute when a claimant digitally certified a claim under the Contract Disputes Act.