Ever had buyer’s remorse or second-guessed a decision? When the U.S. Army Corps of Engineers did that, a Contractor won its claim for time and money.
On a flood control project near Nogales, Arizona, severe flooding delayed and impacted the Project. Thereafter, the Government and Contractor both signed modifications for other changes. Subsequently, the Government internally circulated a draft Mod pertaining to flood-related delays and impacts. Even later, the Government invited and the Contractor submitted an REA for several claim items, including an item for flood-related events. The Government internally considered the REA, but never rendered a decision. (The only failure is not deciding. – Gen. George S. Patton)
When the Contractor appealed to the Court of Federal Claims, the Government argued that the bilateral mods included release language broad enough to be an accord and satisfaction of the flood-related events.
The affirmative defense of accord and satisfaction requires four elements: (1) proper subject matter, (2) competent parties, (3) a meeting of the minds of the parties, and (4) consideration.
The Court held the proper subject matter element was not met when the signed mods were for changes unrelated to the flood. More interestingly, the Court also held the parties did not come to a meeting of the minds (i.e., the parties did not share the same understanding or belief) because after both parties signed the modifications with the release language, the Government continued to consider the Contractor’s flood-related claim item by: (1) internally circulating a draft modification for the flood-related events and (2) requesting and internally considering the Contractor’s REA.
Perhaps the most bothersome fact about all of this is that the Contractor would not have learned about the Government’s continued consideration of its claim for flood-related events had the Contractor given up the fight.
Meridian Engineering Company v. U.S., Court of Federal Claims, No. 11-492C (Sept. 23, 2019).
Roads & Bridges |Let the Contract Lead
LET THE CONTRACT LEAD
Documents offer guidance needed to manage risk without derailing projects
Construction is an industry of managed risk. Whether the prices […]
Roads & Bridges | When is an Invoice Really an Invoice?
WHEN IS AN INVOICE REALLY AN INVOICE?
All court decisions are opinions. Appellate court decisions are typically made by a panel of three […]
Roads & Bridges | Clarifying Punitive Damages
CLARIFYING PUNITIVE DAMAGES
In June 2021, the South Dakota Department of Transportation contracted for the demolition and construction of a bridge on State […]
Roads & Bridges | When Approximate Means Assumed Risk
WHEN APPROXIMATE MEANS ASSUMED RISK
A New York Court Shows How Performance Specifications Can Leave Contractors Holding the Bag
Sometimes when we are told […]
Roads & Bridges | From Roman Arches to AI
FROM ROMAN ARCHES TO AI
Can Construction Evolve Without Risk?
The construction industry blends old with new. From ancient Roman archways and aqueducts and […]
Roads & Bridges | Caught in the Middle
CAUGHT IN THE MIDDLE
New Mexico bridge case highlights the importance of written agreements for changes and delay compensation
In construction contracting, hope for […]
Roads & Bridges | Wait and It’s Waived
WAIT AND IT’S WAIVED
Roads & Bridges | Supreme Court Ruling on Arbitration Delay
Don’t wait to arbitrate! Progressing too far down the litigation […]
Roads & Bridges | Court Defines When Contractors Can Withdraw Due to Mistakes
BIDDING BLUNDER
Roads & Bridges | Court Defines When Contractors Can Withdraw Due to Mistakes
For over 125 years, the vast majority of jurisdictions […]
FEDERAL CONTRACT TERMINATION OR MODIFICATION
The White House has directed Agency heads to “terminate or modify . . . covered contracts.” With some exceptions, there are […]










