LIQUIDATED DAMAGES | Penalties and What is Unenforceable

Liquidated damages typically flow from delays, but they are not always solidly enforced.

In June 2017, a contractor agreed to construct a new park and elementary school for a city. The project included demolition of an existing park.

The city did not want the neighborhood to go without a park for a long period of time. So, the contract included a deadline for completion and a liquidated damages (LDs) clause for delays beyond that deadline ($1,000 per calendar day).

Continue reading…

 

 

Published On: February 24, 2024

Share This Story, Choose Your Platform!

It’s Good to Be the King

October 16, 2018|

Mel Brooks in the movie History of the World: Part I (1981) said it best – “It’s good to be the King.”  It’s also true when asserting claims against the State or an arm or agent of the State.

Manage the Risk of Construction Changes

August 15, 2018|

Almost any problem on a construction project can be traced to one of two things: changes or delays (even delays are really just changes).  As in life, embrace and manage the change don’t run from it.

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!