Too often I’ve heard, “we didn’t want to rock the boat, so we just discussed the problem, but didn’t provide written notice.”  But, remember The Godfather – “It’s not personal, it’s strictly business.”

Under a contract to furnish and install HVAC piping for a U.S. Army training facility at Joint Base Elmendorf-Richardson in Anchorage, Alaska, the Contractor argued the contract drawings and specs lacked the design details necessary to perform the work.  The Contractor submitted several RFIs.

The Government argued the Contractor must use a letter, not an RFI, to notify the Contracting Officer of design problems.  The Board held the information conveyed in the Contractor’s RFIs was sufficient to notify the government of a design discrepancy and “the Board (and the government) should not elevate form over substance in evaluating the sufficiency of a contractor’s notice.”

The Government also argued that the Contractor bore the risk of performing the changed work before the CO responded to the Contractor’s notice.  Holding in the Contractor’s favor, the Board reasoned the risk borne by the Contractor is the risk of an incorrect course of action.  If the Contractor takes the correct course of action (i.e., if it performs the work exactly as the CO would have directed) the Government suffers no harm, so the Contractor bears no such risk.  When the Contractor acts before the CO responds, the Contractor bears the risk of taking incorrect action.  If you’re gonna act, make it the correct action.

This case did not decide which party was at fault for the missing design details (i.e., Spearin Doctrine).  But, [spoiler alert] the Government doesn’t automatically bear such responsibility even if it is a design-bid-build contract.

Appeal of UNIT Company, Armed Services Board of Contract Appeals, No. 60581 (Feb. 12, 2018).

Published On: March 19, 2020

Share This Story, Choose Your Platform!

  • Your Contract Can Handle COVID-19

Your Contract Can Handle COVID-19

April 9, 2020|

Uncertainty and risk are not new or novel to contractors.  Contracts reduce uncertainty and share the risk of doing or providing something.  COVID-19 may have contributed to, but it has not single-handedly created, uncertainty and risk. 

  • Jonathan Straw | Partner Kraftson & Caudle | Heavy Construction Law

Taxes Due!

March 10, 2020|

It’s tax season again, so it’s time to pay the piper.

  • Jonathan Straw | Partner Kraftson & Caudle | Heavy Construction Law

Claim Certified with Digital Signature Deemed OK

February 6, 2020|

The law is not a trend-setter.  It doesn’t readily change or adapt to tech.  So, a commonplace practice in business became a dispute when a claimant digitally certified a claim under the Contract Disputes Act.

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!