Ever had buyer’s remorse or second-guessed a decision? When the U.S. Army Corps of Engineers did that, a Contractor won its claim for time and money.
On a flood control project near Nogales, Arizona, severe flooding delayed and impacted the Project. Thereafter, the Government and Contractor both signed modifications for other changes. Subsequently, the Government internally circulated a draft Mod pertaining to flood-related delays and impacts. Even later, the Government invited and the Contractor submitted an REA for several claim items, including an item for flood-related events. The Government internally considered the REA, but never rendered a decision. (The only failure is not deciding. – Gen. George S. Patton)
When the Contractor appealed to the Court of Federal Claims, the Government argued that the bilateral mods included release language broad enough to be an accord and satisfaction of the flood-related events.
The affirmative defense of accord and satisfaction requires four elements: (1) proper subject matter, (2) competent parties, (3) a meeting of the minds of the parties, and (4) consideration.
The Court held the proper subject matter element was not met when the signed mods were for changes unrelated to the flood. More interestingly, the Court also held the parties did not come to a meeting of the minds (i.e., the parties did not share the same understanding or belief) because after both parties signed the modifications with the release language, the Government continued to consider the Contractor’s flood-related claim item by: (1) internally circulating a draft modification for the flood-related events and (2) requesting and internally considering the Contractor’s REA.
Perhaps the most bothersome fact about all of this is that the Contractor would not have learned about the Government’s continued consideration of its claim for flood-related events had the Contractor given up the fight.
Meridian Engineering Company v. U.S., Court of Federal Claims, No. 11-492C (Sept. 23, 2019).
Are We There Yet?
Next time you close a deal, get the essential terms on paper and signed by all parties before it’s Miller Time.
Show Me the Money!
You told the guy to do the work, the work is done, and now it’s time for payment, right? But, you only told […]
Reasonable ≠ Ratio
“Circuit court litigation comes at a price, sometimes a heavy price.”
Words Matter
Remember the adage, “what you say today could bite you tomorrow.”
Recently, a Contractor won its argument before the Armed Services Board of […]
Run Through the Base, Not To the Base
Run Through the Base, Not To the Base
Thankfully, baseball season is back. While listening to a broadcast of my favorite team yesterday, […]
Having Your Cake and Eating It Too: Attorneys Fees Without a Contract Clause
How often have you wanted to take a dispute “to the mattresses” (think, The Godfather), but the cost was prohibitive? You have […]
Choose Your Own Venue: Where to File a Miller Act Lawsuit
Do you remember the Choose Your Own Adventure books? If you are a subcontractor on a federal project, where should you […]
Speak Now or Pay Later
This applies to general contractors, subcontractors, and suppliers. Each can be the party preparing and transmitting a form of purchase order or […]
General Contractors Waive Goodbye
General Contractors: When was the last time a private owner asked you to waive your lien rights before you did any work? […]