The law is not a trend-setter. It doesn’t readily change or adapt to tech. So, a commonplace practice in business became a dispute when a claimant digitally certified a claim under the Contract Disputes Act.
The Claimant/Contractor had a contract for maintenance, modification, and repair of aircraft weapons systems for the U.S. Air Force. Per FAR § 52.233-1, the Contractor certified its claim by applying a digital signature, much like those applied through Adobe Acrobat, DocuSign, or similar software:

A claim certification signature must be verifiable – identification that something is, in fact, uniquely true and accurate. For example, you have probably looked at your signature on a document and simply known whether it was, in fact, your signature or if somebody else tried to sign for you. Most importantly, whatever it was that convinced you of the authenticity, it was unique (e.g., a certain swirl or flourish in your signature, or lack thereof). Signatures are uniquely identifiable and; therefore, verifiable.
The Government argued the Contractor’s digital signature could not be “verified” on the claim certification and that lack of uniqueness made the certification incomplete. The signature part of a claim certification is important to show that the claimant, and not someone else purporting to be the claimant, intended the claim to be true and accurate.
The Armed Services Board of Contract Appeals held the digital signature was sufficiently unique. Even though the digital signature was type-written, it could not have been applied without first inputting at least one unique password into the software platform.
In another opinion, the Board held that a simple, typewritten name is insufficient to certify a claim because no password is needed to simply type your name (e.g., in an e-mail signature block). But, in that case, the Board didn’t consider that the e-mail sender likely had to input a password to access and send the e-mail.
Traditional physical signatures are still okay. To be safe, stick with tried and true methods when dealing with legal matters. The law is slow to catch-up with technology.
Appeal of URS Federal Services, Inc., Armed Services Board of Contract Appeals No. 61443 (Oct. 3, 2019)
Acceptance and Intervening Cause Avoided Construction Warranty Claim
Like cars, computers, and appliances, construction projects include warranties too. Similarly, construction project warranties are limited to causes within the contractor’s control […]
Insurance Company Had No Duty to Defend Under Eight Corners Rule
To decide if an insurer has a duty to defend, a Virginia State or Federal Court may only look at the allegations in the complaint and the insurance policy to determine if a judgment against the insured will be covered by the policy.
Owner SOL When Mandatory Mediation Didn’t Toll Statute of Limitations
Contract interpretation strives to find the meaning of all parts together.
Government Must Review Claims in Good Faith, Not “Conjure Up” a “Baseless Retaliation”
A contracting officer’s review of certified claims submitted in good faith is not intended to be a negotiating game where the agency may deny meritorious claims to gain leverage over the contractor.
Termination for Convenience was OK to Get a Lower Price
When Massachusetts’ highest State court rejected Federal law on termination for convenience (T4C) a public entity’s “sole discretion . . . for […]
Pirates (Parties) Should Arbitrate Arbitrability
Yes, the word “pirates” is an anagram for “parties.” Participants in a lawsuit, arbitration, or mediation are collectively referred to as parties. Are they pirates too?
Very Bad Behavior Without Bad Faith is Not a Breach of Contract
Despite “abhorrent” behavior by the Army Corps of Engineers, a majority of the Armed Services Board of Contract Appeals held there was […]
Government Construction Contracts Require Bonds, Even When Contract Doesn’t Say So
Yesterday (Nov. 5, 2018), the Fed. Cir. Ct. of Appeals again endorsed the Christian doctrine, which can make unstated requirements part of a government contract.
Government’s Negligent Estimate a Trick?
The Government’s negligent estimate failed to provide the “most current information available.”