In Washington D.C., a private Owner sued its Designer alleging professional negligence arising from the construction of $10 million tennis and education facility.  Among other issues, the court held the Owner’s professional negligence claim was late as it was filed more than three years after accrual (D.C. Code § 12-301(3)).

The contract required:

  • a request for mediation before filing a lawsuit and
  • that any lawsuit must be filed within three years.

The Owner unsuccessfully argued that only its request for mediation was necessary within three years.  Yet, a related provision of the contract stated that a mediation request could be made at the same time as the filing of a lawsuit.  If a mediation request tolled the statute, this related provision would be meaningless.

Contract interpretation strives to find the meaning of all parts together.  So, when you think you’ve found the right answer in your contract, keep reading all parts together to be certain.  (Read Related Post.)

Washington Tennis & Education Foundation, Inc. v. Clark Nexsen, Inc., 324 F.Supp.3d 128 (U.S. Dist. Ct., D.C., Aug. 20, 2018)

Published On: February 20, 2019

Share This Story, Choose Your Platform!

Owner Nonpayment is No Defense to Miller Act Claim

October 24, 2017|

As if you needed confirmation that the Federal Miller Act is a powerful tool for unpaid subcontractors, this is it.  Even when a Prime ordered and accepted the Sub’s work, but didn’t have to pay under the Subcontract, the Subcontractor still. . . .

Trust, but Verify

October 17, 2017|

Rely at your own risk upon a Contracting Officer’s statements when statutes or contract provisions may conflict.

Bases Covered?

August 8, 2017|

Contractors, will your current insurance policy cover “your work” as a joint venture partner? The typical answer is NO. 

Rules, Which Rules?

July 25, 2017|

Good Idea: Include a choice of law clause in your contract to promote consistency and predictability (while reducing potential costs and risk).

Government Liability for Third-Party Delays

July 18, 2017|

Generally, the Government is not responsible for delays caused by third parties, even other contractors at its own project site, unless the Government affirmatively indicates the site will be ready and available. 

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!