As if you needed confirmation that the Federal Miller Act is a powerful tool for unpaid subcontractors, this is it. Even when a Prime ordered and accepted the Sub’s work, but didn’t have to pay under the Subcontract, the Subcontractor still got paid by the Prime’s Surety.
On a project for the U.S. Army Corps of Engineers in Qatar, a Subcontractor agreed to provide labor and materials for telecommunication systems. The Prime ordered and accepted a portion of the work and the Sub performed. The Corps then terminated the Prime for default, so the Prime refused to pay the Sub.
The Prime breached the Subcontract but because of its termination by the Corps and terms of the Subcontract, the Prime was not on the hook for any damages to the Sub. Notably, the Court stated that, if “the Court were to base its decision on whether a party had acted unprofessionally towards another party, had mislead another party (whether intentionally or not), or had wrongly accused another party of failing to perform under a contract, then the court would find the [Prime should pay the Sub].” But, the Court’s jurisdiction is limited to interpreting and applying only the applicable law, including the parties’ agreement.
However, under the Federal Miller Act, the Prime’s Surety was liable for the full amount of damages. The Surety’s liability is independent of its Principal’s liability and required only a showing that the Sub had performed the work and had not been paid.
Pragmatically, the Surety will pay the Sub and then demand reimbursement from its Principal, the Prime.
U.S. f/u/b/o VT Milcom, Inc. v. PAT USA, Inc., Case No. 5:16-cv-00007, (W.D. Va., July 14, 2017).
Roads & Bridges
Where Does the Buck Stop?
Jon is a monthly contributor to Roads & Bridges magazine. He has been writing the law section for the magazine since January 2020. The link below will take you directly to the Roads & Bridges […]
Pay-If-Paid Unenforceable in Virginia Starting Jan. 1, 2023
As of Jan. 1, 2023, pay-if-paid clauses are unenforceable, regardless of whether a surety/payment bond claim is involved. This is only for subcontracts created on/after 1/1/23.
Also for subcontracts created on/after 1/1/23, the prime must specifically […]
How Short is Too Short
A limitations period is too short when it’s unreasonably short.
Construction Contracting Without Relief Clauses During COVID-19
What to do if your contract lacks the parts to handle COVID-19? Considerations for creating new contracts during COVID-19.
Your Contract Can Handle COVID-19
Uncertainty and risk are not new or novel to contractors. Contracts reduce uncertainty and share the risk of doing or providing something. COVID-19 may have contributed to, but it has not single-handedly created, uncertainty and risk.
Contractors Can Use RFI to Notify the Government
The Board (and the government) should not elevate form over substance in evaluating the sufficiency of a contractor’s notice.
Taxes Due!
It’s tax season again, so it’s time to pay the piper.
Contractor Wins when Government Reconsiders Accord
Ever had buyer’s remorse or second-guessed a decision? When the U.S. Army Corps of Engineers did that, a Contractor won its claim for time and money.
On a flood control project near Nogales, Arizona, severe flooding […]
Claim Certified with Digital Signature Deemed OK
The law is not a trend-setter. It doesn’t readily change or adapt to tech. So, a commonplace practice in business became a dispute when a claimant digitally certified a claim under the Contract Disputes Act.

Jonathan J. Straw
Blog Author
Contact Jonathan
Partner | KraftsonCaudle.com
Download Jon’s Bio
