Requirements may exist outside the four corners of the contract when such requirements are: (1) otherwise mandatory and (2) express a significant or deeply ingrained strand of public procurement policy. In other words, your contract may include requirements not shown or otherwise indicated in the contract documents.
In an example of this, a Contractor agreed to provide pre-engineered metal buildings for the Army’s use at Camp Edwards, Massachusetts. Under the Miller Act and the FAR, bonds for construction projects are mandatory. The mandate for payment bonds is based upon the “deeply ingrained strand of public procurement policy” that security should be provided for entities or persons furnishing labor and materials in the performance of government contracts. The mandate for performance bonds is due to the Government’s need for security to ensure the use of public funds results in a finished product since not completing a public project could be a waste or misuse of public funds. Of course, (dripping with sarcasm) we’ve never seen a public entity waste or misuse public funds, right.
The Armed Services Board of Contract Appeals held bonds were part of the contract even though bonding requirements were not expressly stated nor incorporated by reference. The U.S. Court of Appeals for the Federal Circuit agreed with the Board. K-Con, Inc. v. Secretary of the Army, U.S. Court of Appeals for the Federal Circuit, Case No.: 2017-2254 (Nov. 5, 2018).
Next time you review an RFP, carefully consider what you don’t see but that may still be required.
Read another short example here: Adding Terms to a Government Contract without Saying So.
How Short is Too Short
A limitations period is too short when it’s unreasonably short.
Construction Contracting Without Relief Clauses During COVID-19
What to do if your contract lacks the parts to handle COVID-19? Considerations for creating new contracts during COVID-19.
Your Contract Can Handle COVID-19
Uncertainty and risk are not new or novel to contractors. Contracts reduce uncertainty and share the risk of doing or providing something. COVID-19 may have contributed to, but it has not single-handedly created, uncertainty and risk.
Contractors Can Use RFI to Notify the Government
The Board (and the government) should not elevate form over substance in evaluating the sufficiency of a contractor’s notice.
Taxes Due!
It’s tax season again, so it’s time to pay the piper.
Contractor Wins when Government Reconsiders Accord
Ever had buyer’s remorse or second-guessed a decision? When the U.S. Army Corps of Engineers did that, a Contractor won its claim […]
Claim Certified with Digital Signature Deemed OK
The law is not a trend-setter. It doesn’t readily change or adapt to tech. So, a commonplace practice in business became a dispute when a claimant digitally certified a claim under the Contract Disputes Act.
Acceptance and Intervening Cause Avoided Construction Warranty Claim
Like cars, computers, and appliances, construction projects include warranties too. Similarly, construction project warranties are limited to causes within the contractor’s control […]
Insurance Company Had No Duty to Defend Under Eight Corners Rule
To decide if an insurer has a duty to defend, a Virginia State or Federal Court may only look at the allegations in the complaint and the insurance policy to determine if a judgment against the insured will be covered by the policy.