We all know what happens when we “ASS-U-ME” something.  So, we should all carefully avoid assuming things unnecessarily.

The prime contractor described below recovered its costs by properly not assuming a duty.  This required a distinction among duties that:

  • must be done;
  • should be done; or
  • need not be done.

On a project for the Florida Department of Transportation, the Prime Contractor terminated its landscaping subcontractor for default after the obligatory 72-hour cure period passed.  The Prime then promptly submitted a performance bond claim to the terminated sub’s surety.  The Prime was obligated to and did wait the 15-day “grace period” for the surety to investigate and respond.  However, when the surety failed to substantively respond, the Prime properly mitigated its damages by engaging a replacement subcontractor.

Upon completion of the replacement subcontractor’s work, the Prime submitted its recoverable costs to the defaulted sub’s surety.  The surety denied payment by arguing the Prime failed to assist with the surety’s investigation of the default.  The Court awarded summary judgment to the Prime finding it had no duty to assist with the surety’s investigation absent an express requirement, which was not included in the bond or subcontract.

The Court agreed that the Prime need not help the surety with the heavy lifting of investigating the sub’s termination for default.

Developers Surety & Indemnity Co. v. Archer Western Contractors, LLC, Case No. 6:16-cv-1875, U.S. Dist. Ct., Mid. Dist. Fl. (May 7, 2018).

Published On: October 24, 2018

Share This Story, Choose Your Platform!

  • Your Contract Can Handle COVID-19

Your Contract Can Handle COVID-19

April 9, 2020|

Uncertainty and risk are not new or novel to contractors.  Contracts reduce uncertainty and share the risk of doing or providing something.  COVID-19 may have contributed to, but it has not single-handedly created, uncertainty and risk. 

  • Jonathan Straw | Partner Kraftson & Caudle | Heavy Construction Law

Taxes Due!

March 10, 2020|

It’s tax season again, so it’s time to pay the piper.

  • Jonathan Straw | Partner Kraftson & Caudle | Heavy Construction Law

Claim Certified with Digital Signature Deemed OK

February 6, 2020|

The law is not a trend-setter.  It doesn’t readily change or adapt to tech.  So, a commonplace practice in business became a dispute when a claimant digitally certified a claim under the Contract Disputes Act.

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!