We all know what happens when we “ASS-U-ME” something. So, we should all carefully avoid assuming things unnecessarily.
The prime contractor described below recovered its costs by properly not assuming a duty. This required a distinction among duties that:
- must be done;
- should be done; or
- need not be done.
On a project for the Florida Department of Transportation, the Prime Contractor terminated its landscaping subcontractor for default after the obligatory 72-hour cure period passed. The Prime then promptly submitted a performance bond claim to the terminated sub’s surety. The Prime was obligated to and did wait the 15-day “grace period” for the surety to investigate and respond. However, when the surety failed to substantively respond, the Prime properly mitigated its damages by engaging a replacement subcontractor.
Upon completion of the replacement subcontractor’s work, the Prime submitted its recoverable costs to the defaulted sub’s surety. The surety denied payment by arguing the Prime failed to assist with the surety’s investigation of the default. The Court awarded summary judgment to the Prime finding it had no duty to assist with the surety’s investigation absent an express requirement, which was not included in the bond or subcontract.
The Court agreed that the Prime need not help the surety with the heavy lifting of investigating the sub’s termination for default.
Roads & Bridges | Mediation Melee
MEDIATION MELEE| An arbitration case can be costly
Arbitration can be a bridge over troubled waters. In this crossing, the parties argued over […]
Roads & Bridges | Written Notice
WRITTEN NOTICE | Beware that strict compliance of the contract might be required.
When an owner replaced a contractor for significant safety violations, […]
Roads & Bridges | Mommie Dearest
MOMMY DEAREST | The story of an ESA without a MOM
Nobody enters this world, or a contract, without a mother: There can […]
IIJA | Does Closing a “Giant Loophole” Cost Contractors?
A recent article published by Roads and Bridges magazine reports that the Office of Management and Budget is working to broaden the scope […]
Roads & Bridges | Buy American Plan Gets an Update
BUY AMERICAN PLAN GETS AN UPDATE
The Office of Management and Budget is developing standards to replace the current Buy […]
Roads & Bridges
Where Does the Buck Stop?
WHERE DOES THE BUCK STOP? | A shallow concrete pour leads to an interesting lawsuit
On the desk of President Harry S. Truman […]
Roads & Bridges | Reshaping Agreements
RESHAPING AGREEMENTS | Oral Agreements Must Be Written in Stone
Reuse, reshaping, and/or reapplication of existing materials was the goal in this roadway […]
Pay-If-Paid Unenforceable in Virginia Starting Jan. 1, 2023
As of Jan. 1, 2023, pay-if-paid clauses are unenforceable, regardless of whether a surety/payment bond claim is involved. This is only for […]
How Short is Too Short
A limitations period is too short when it’s unreasonably short.










