What to do when the drawings indicate one thing while the specifications require something different?

On a federal construction project, the specifications trump the drawings. (Federal Acquisition Regulations 52.236-21(a)).  But, remember these things too:

  1. Always ask sooner rather than later about obvious differences.
  2. If the difference is patent (i.e., apparent on its face) and you haven’t submitted a bid yet, then pose the question or risk misinterpreting.
  3. If the difference is latent (i.e., not apparent on its face, but only upon learning additional information and capable of more than one reasonable interpretation), then you probably won’t (and hopefully can’t) discover it until after contract award.

In any event, you should promptly notify the Contracting Officer and Designer of Record upon discovery of any discrepancies.

Eggs

Published On: February 7, 2018

Share This Story, Choose Your Platform!

Are We There Yet?

May 8, 2017|

Next time you close a deal, get the essential terms on paper and signed by all parties before it’s Miller Time.

Show Me the Money!

May 1, 2017|

You told the guy to do the work, the work is done, and now it’s time for payment, right?  But, you only told […]

Reasonable ≠ Ratio

April 24, 2017|

“Circuit court litigation comes at a price, sometimes a heavy price.”

Words Matter

April 17, 2017|

Remember the adage, “what you say today could bite you tomorrow.”

Recently, a Contractor won its argument before the Armed Services Board of […]

Speak Now or Pay Later

June 5, 2015|

This applies to general contractors, subcontractors, and suppliers.  Each can be the party preparing and transmitting a form of purchase order or […]

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!