Here’s the situation – You’ve done the extra work because you were verbally asked and you strive to do a good job. But now, the Owner or Prime won’t pay because your Contract or Subcontract precludes payment without a written change order.
Even if your agreement can only be modified by a writing, you may still have a good argument to be paid for extra work.
Consider your prior dealings with the Owner or Prime on the current project and on prior projects. Have you ever been paid for extra work without a written change order? If yes, then you could still get paid even though the contract requires a written change order or other written agreement. The more frequently this happens between you and the other party, the better your chances of payment.
The Virginia Supreme Court has held a subcontract clause requiring a written agreement for changes did not pertain to work outside the scope of the original subcontract. Instead, the Subcontractor’s invoices were sufficient written documentation to show subsequent, separate agreements for the extra work. The Subcontractor’s daily reports supported that the Subcontractor actually performed the extra work. Also important is that the subcontract did not include a provision that excluded all other negotiations from the Subcontract (i.e., a merger or integration clause).
Medlin & Son Construction Co. v. The Matthews Group, Inc., No. 160050 (Va. Nov. 23, 2016)
Termination of Government Contracts for Convenience (T4C)
Imagine you’re a Government Contractor under a firm, fixed-price contract and you’ve done nothing wrong. Nevertheless, the Government has decided to unilaterally end its contract with you. Yes, the Government can do this...
Government Contractors: Build a Snowman in August
As a Government Contractor, when have you agreed to perform a certain way, but later realized that another way is better for everybody? When the Government agrees, expressly or impliedly, to the alternative performance, it waives a credit for the unperformed work.
Construction Dispute Settlement: Dealing with Details
Reap the benefits of settling a construction dispute by doing these things.
E-mail Signature Not Enough to Certify a Claim
Construction project professionals routinely send e-mails with “signatures,” which typically include the sender’s typewritten name, title, contact information, and/or company logo. But, this sort of e-mail “signature” is not enough to certify a claim to the Government.
Government Contractors: Ask for a “Sum Certain” in Your Claim
If your Claim includes an item for damages with an amount “TBD,” you could lose the entire Claim.
Contractors: Be Aware When Contracting with Virginia Public Agencies
Without a valid contract, a Virginia public entity has no duty to to pay for any of your work.
Constructive Acceleration
Contractors know that time is money. So, the point is clear when expressly told to “Speed Up! Go Faster!”
But, what do you […]
Construction Contracts & Whodunit
Imagine reading a crime novel and just when you think you figured out whodunit, a plot twist suggests a different culprit. In construction contracting, finding the right answer can be a difficult task when
Trick or Treat in Government Contract Claims
Without a request for a contracting officer’s final decision, claimants may seek treats, but get tricked instead.