“Two roads diverged in a wood, and . . .” the Prime Contractor had to take both roads at the same time to the same place.
Problem Example
Subcontractor on project for the U.S. Army Corps of Engineers at Ft. Lee, Virginia, sued Prime Contractor and Surety for nonpayment under the Federal Miller Act. Prime and Surety wanted to pause (stay) the litigation while pursuing arbitration. The Court granted a stay of the litigation for the Prime. The Court denied the stay of the litigation for the Surety because:
- The Surety was not obligated under any written agreement to arbitrate and
- The Surety’s liability under the Miller Act is independent of the Prime’s liability (these two facts are true in most instances).
In other words, even if the Prime owes nothing to the Subcontractor, the Surety could still owe payment to the Subcontractor if the lawsuit was timely filed, the work was done, and the Subcontractor was not already paid. In this case, the Prime had to pay for the Surety’s defense (a typical obligation) in the litigation while simultaneously paying for its own arbitration defense.
Potential Solution(s)
To avoid/reduce this dual-track approach/cost, prime contractors can:
- Seek the surety’s prior written agreement to arbitrate;
- Apply the American Arbitration Association’s Fast Track Procedures if the disputed amount is less than $100,000; or
- Require Alternative Dispute Resolution before any litigation (this will work in the Federal First Circuit (ME, NH, MA, and RI), but may not work in all Federal Courts). (Caution: Requiring arbitration of a Miller Act dispute will not pause the one-year statute of limitations to file a Miller Act lawsuit.)
Forum Selection Can Be a Home-Court Advantage
I promise that any disputes between us will be argued at your house. Time passes and a dispute begins to brew. Now, I want to argue at my house, not at yours. You pay costs to argue at my house that you wouldn’t have incurred had I done as agreed. Should I have to reimburse your costs?
No-Damage-for-Delay and Owner-Related Dispute Clauses are No Defense to Surety Liability Under Miller Act
Prime Government Contractors - you may need to update your interim payment waivers.
Contractual Fairness is Whatever the Parties’ Agreed
When you know a current action or inaction is wrong, but you do not object, should you be allowed to object later?
Which Comes First – Specifications or Drawings?
Sometimes it's not better to ask for forgiveness after-the-fact.
Government Contract Claims: When Appeal is Rejection of Settlement
Without a reservation of rights, appealing a Contracting Officer’s Final Decision is a rejection of any offer of payment or settlement included therein. So, the contractor had only three options.
Linking Obligations
If you want to bind the subcontractor to the prime in every way the same as the prime is bound to the owner, then the incorporation clause of the subcontract should be: . . .
Termination of Government Contracts for Convenience (T4C)
Imagine you’re a Government Contractor under a firm, fixed-price contract and you’ve done nothing wrong. Nevertheless, the Government has decided to unilaterally end its contract with you. Yes, the Government can do this...
Government Contractors: Build a Snowman in August
As a Government Contractor, when have you agreed to perform a certain way, but later realized that another way is better for everybody? When the Government agrees, expressly or impliedly, to the alternative performance, it waives a credit for the unperformed work.
Construction Dispute Settlement: Dealing with Details
Reap the benefits of settling a construction dispute by doing these things.










