A mentor of mine once said that process and procedures can be more important than substance and results. Like solving a math problem, how you solve it is often more important than the answer itself. The same is true in resolving construction contract disputes with public owners.
Under a contract with the City of Baltimore, the Contractor agreed to complete an administrative dispute resolution process before suing the City. But, without first completing the administrative process, the Contractor sued the City. The Contractor tried to justify its lawsuit by arguing that the City had also agreed to follow an administrative process before it could assess liquidated damages and that the City was the first to breach the contract by not following that administrative process. (Being the first to breach the contract may excuse another party’s later breach of the same contract.)
The Court did not have to decide if the City first breached the contract because the Court decided the Contractor didn’t properly follow the administrative process before suing the City.
The Contractor has not lost the war, but it lost this battle, time, and money. Follow the process even if it appears unnecessary. As a math teacher might say, “show your work.”
Owner Nonpayment is No Defense to Miller Act Claim
As if you needed confirmation that the Federal Miller Act is a powerful tool for unpaid subcontractors, this is it. Even when a Prime ordered and accepted the Sub’s work, but didn’t have to pay under the Subcontract, the Subcontractor still. . . .
Trust, but Verify
Rely at your own risk upon a Contracting Officer’s statements when statutes or contract provisions may conflict.
Payment for Verbal Changes When a Writing was “Required”
Even if your agreement can only be modified by a writing, you may still have a good argument to be paid for extra work.
Pirates and Arbitration
How does a pirate solve a dispute (besides walking the plank)?
Bases Covered?
Contractors, will your current insurance policy cover “your work” as a joint venture partner? The typical answer is NO.
Two Paths at the Same Time to the Same Place
“Two roads diverged in a wood, and . . .” the Prime Contractor had to take both roads at the same time to the same place.
Rules, Which Rules?
Good Idea: Include a choice of law clause in your contract to promote consistency and predictability (while reducing potential costs and risk).
Government Liability for Third-Party Delays
Generally, the Government is not responsible for delays caused by third parties, even other contractors at its own project site, unless the Government affirmatively indicates the site will be ready and available.
Keep a Pass-Thru Claim Burning, Don’t Extinguish Liability
Prime contractors, have you ever submitted a subcontractor’s claim to a public owner? Subcontractors, have you ever wanted to submit a claim against the government, but you had no contract with government?










