A mentor of mine once said that process and procedures can be more important than substance and results.  Like solving a math problem, how you solve it is often more important than the answer itself.  The same is true in resolving construction contract disputes with public owners.

Under a contract with the City of Baltimore, the Contractor agreed to complete an administrative dispute resolution process before suing the City.  But, without first completing the administrative process, the Contractor sued the City.  The Contractor tried to justify its lawsuit by arguing that the City had also agreed to follow an administrative process before it could assess liquidated damages and that the City was the first to breach the contract by not following that administrative process.  (Being the first to breach the contract may excuse another party’s later breach of the same contract.)

The Court did not have to decide if the City first breached the contract because the Court decided the Contractor didn’t properly follow the administrative process before suing the City.

The Contractor has not lost the war, but it lost this battle, time, and money.  Follow the process even if it appears unnecessary.  As a math teacher might say, “show your work.”

Balfour Beatty Infrastructure, Inc. v. Mayor and City Council of Baltimore, Appeal No. 16-1322 (4th Cir., Apr. 25, 2017)

Published On: June 19, 2017

Share This Story, Choose Your Platform!

Owner Nonpayment is No Defense to Miller Act Claim

October 24, 2017|

As if you needed confirmation that the Federal Miller Act is a powerful tool for unpaid subcontractors, this is it.  Even when a Prime ordered and accepted the Sub’s work, but didn’t have to pay under the Subcontract, the Subcontractor still. . . .

Trust, but Verify

October 17, 2017|

Rely at your own risk upon a Contracting Officer’s statements when statutes or contract provisions may conflict.

Bases Covered?

August 8, 2017|

Contractors, will your current insurance policy cover “your work” as a joint venture partner? The typical answer is NO. 

Rules, Which Rules?

July 25, 2017|

Good Idea: Include a choice of law clause in your contract to promote consistency and predictability (while reducing potential costs and risk).

Government Liability for Third-Party Delays

July 18, 2017|

Generally, the Government is not responsible for delays caused by third parties, even other contractors at its own project site, unless the Government affirmatively indicates the site will be ready and available. 

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!