MAXIMIZING DAMAGE RECOVERY
Tracking Costs, Avoiding Duplication in Liquidated and Actual Damage Claims

A County and Contractor contracted for construction of a road and drainage improvement project. The planned project duration was 180 days. The Contractor delayed and defaulted. The Contractor’s surety entered into a takeover agreement with the County to complete the project. Continue reading…

Published On: March 6, 2025

Share This Story, Choose Your Platform!

Construction Contracts & Whodunit

November 7, 2017|

Imagine reading a crime novel and just when you think you figured out whodunit, a plot twist suggests a different culprit. In construction contracting, finding the right answer can be a difficult task when

Owner Nonpayment is No Defense to Miller Act Claim

October 24, 2017|

As if you needed confirmation that the Federal Miller Act is a powerful tool for unpaid subcontractors, this is it.  Even when a Prime ordered and accepted the Sub’s work, but didn’t have to pay under the Subcontract, the Subcontractor still. . . .

Trust, but Verify

October 17, 2017|

Rely at your own risk upon a Contracting Officer’s statements when statutes or contract provisions may conflict.

Bases Covered?

August 8, 2017|

Contractors, will your current insurance policy cover “your work” as a joint venture partner? The typical answer is NO. 

Rules, Which Rules?

July 25, 2017|

Good Idea: Include a choice of law clause in your contract to promote consistency and predictability (while reducing potential costs and risk).

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!