Another post discussed that your existing contract can probably handle the risks related to COVID-19.  But, what to do if you contract lacks the support to handle COVID-19 and what to consider when creating new contracts during COVID-19?

What if the contract does not have a force majeure or other relief clause?  First, consider the language of any applicable changes clause.  Second, review any governmental emergency relief acts that could help.  Third, the common law doctrine of frustration may be available, under which an obligation may excused or discharged when a fundamental assumption of the contract is not true or something later occurs rendering performance physically impossible or commercially impracticable.  However, a radical price increase alone is likely insufficient.

When creating new contracts during COVID-19, do not rely solely upon force majeure clauses.  Because unforeseeability is an element of most clauses, parties contracting during an event will find it very difficult to argue they could not contemplate the potential impact of the event.  Consider including or adapting a price acceleration provision to prescribe or liquidate relief.

Published On: April 15, 2020

Share This Story, Choose Your Platform!

Linking Obligations

January 24, 2018|

If you want to bind the subcontractor to the prime in every way the same as the prime is bound to the owner, then the incorporation clause of the subcontract should be: . . .

Termination of Government Contracts for Convenience (T4C)

January 16, 2018|

Imagine you’re a Government Contractor under a firm, fixed-price contract and you’ve done nothing wrong.  Nevertheless, the Government has decided to unilaterally end its contract with you.  Yes, the Government can do this...

Government Contractors: Build a Snowman in August

January 8, 2018|

As a Government Contractor, when have you agreed to perform a certain way, but later realized that another way is better for everybody?  When the Government agrees, expressly or impliedly, to the alternative performance, it waives a credit for the unperformed work.

E-mail Signature Not Enough to Certify a Claim

December 5, 2017|

Construction project professionals routinely send e-mails with “signatures,” which typically include the sender’s typewritten name, title, contact information, and/or company logo.  But, this sort of e-mail “signature” is not enough to certify a claim to the Government.

Constructive Acceleration

November 14, 2017|

Contractors know that time is money.  So, the point is clear when expressly told to “Speed Up!  Go Faster!”

But, what do you […]

Construction Contracts & Whodunit

November 7, 2017|

Imagine reading a crime novel and just when you think you figured out whodunit, a plot twist suggests a different culprit. In construction contracting, finding the right answer can be a difficult task when