Ever had buyer’s remorse or second-guessed a decision? When the U.S. Army Corps of Engineers did that, a Contractor won its claim for time and money.
On a flood control project near Nogales, Arizona, severe flooding delayed and impacted the Project. Thereafter, the Government and Contractor both signed modifications for other changes. Subsequently, the Government internally circulated a draft Mod pertaining to flood-related delays and impacts. Even later, the Government invited and the Contractor submitted an REA for several claim items, including an item for flood-related events. The Government internally considered the REA, but never rendered a decision. (The only failure is not deciding. – Gen. George S. Patton)
When the Contractor appealed to the Court of Federal Claims, the Government argued that the bilateral mods included release language broad enough to be an accord and satisfaction of the flood-related events.
The affirmative defense of accord and satisfaction requires four elements: (1) proper subject matter, (2) competent parties, (3) a meeting of the minds of the parties, and (4) consideration.
The Court held the proper subject matter element was not met when the signed mods were for changes unrelated to the flood. More interestingly, the Court also held the parties did not come to a meeting of the minds (i.e., the parties did not share the same understanding or belief) because after both parties signed the modifications with the release language, the Government continued to consider the Contractor’s flood-related claim item by: (1) internally circulating a draft modification for the flood-related events and (2) requesting and internally considering the Contractor’s REA.
Perhaps the most bothersome fact about all of this is that the Contractor would not have learned about the Government’s continued consideration of its claim for flood-related events had the Contractor given up the fight.
Meridian Engineering Company v. U.S., Court of Federal Claims, No. 11-492C (Sept. 23, 2019).
Construction Dispute Settlement: Dealing with Details
Reap the benefits of settling a construction dispute by doing these things.
E-mail Signature Not Enough to Certify a Claim
Construction project professionals routinely send e-mails with “signatures,” which typically include the sender’s typewritten name, title, contact information, and/or company logo. But, this sort of e-mail “signature” is not enough to certify a claim to the Government.
Government Contractors: Ask for a “Sum Certain” in Your Claim
If your Claim includes an item for damages with an amount “TBD,” you could lose the entire Claim.
Contractors: Be Aware When Contracting with Virginia Public Agencies
Without a valid contract, a Virginia public entity has no duty to to pay for any of your work.
Constructive Acceleration
Contractors know that time is money. So, the point is clear when expressly told to “Speed Up! Go Faster!”
But, what do you […]
Construction Contracts & Whodunit
Imagine reading a crime novel and just when you think you figured out whodunit, a plot twist suggests a different culprit. In construction contracting, finding the right answer can be a difficult task when
Trick or Treat in Government Contract Claims
Without a request for a contracting officer’s final decision, claimants may seek treats, but get tricked instead.
Owner Nonpayment is No Defense to Miller Act Claim
As if you needed confirmation that the Federal Miller Act is a powerful tool for unpaid subcontractors, this is it. Even when a Prime ordered and accepted the Sub’s work, but didn’t have to pay under the Subcontract, the Subcontractor still. . . .
Trust, but Verify
Rely at your own risk upon a Contracting Officer’s statements when statutes or contract provisions may conflict.










