Ever had buyer’s remorse or second-guessed a decision?  When the U.S. Army Corps of Engineers did that, a Contractor won its claim for time and money.

On a flood control project near Nogales, Arizona, severe flooding delayed and impacted the Project.  Thereafter, the Government and Contractor both signed modifications for other changes.  Subsequently, the Government internally circulated a draft Mod pertaining to flood-related delays and impacts.  Even later, the Government invited and the Contractor submitted an REA for several claim items, including an item for flood-related events.  The Government internally considered the REA, but never rendered a decision.  (The only failure is not deciding. – Gen. George S. Patton)

When the Contractor appealed to the Court of Federal Claims, the Government argued that the bilateral mods included release language broad enough to be an accord and satisfaction of the flood-related events.

The affirmative defense of accord and satisfaction requires four elements: (1) proper subject matter, (2) competent parties, (3) a meeting of the minds of the parties, and (4) consideration.

The Court held the proper subject matter element was not met when the signed mods were for changes unrelated to the flood.  More interestingly, the Court also held the parties did not come to a meeting of the minds (i.e., the parties did not share the same understanding or belief) because after both parties signed the modifications with the release language, the Government continued to consider the Contractor’s flood-related claim item by: (1) internally circulating a draft modification for the flood-related events and (2) requesting and internally considering the Contractor’s REA.

Perhaps the most bothersome fact about all of this is that the Contractor would not have learned about the Government’s continued consideration of its claim for flood-related events had the Contractor given up the fight.

Meridian Engineering Company v. U.S., Court of Federal Claims, No. 11-492C (Sept. 23, 2019).

Published On: February 26, 2020

Share This Story, Choose Your Platform!

  • Your Contract Can Handle COVID-19

Your Contract Can Handle COVID-19

April 9, 2020|

Uncertainty and risk are not new or novel to contractors.  Contracts reduce uncertainty and share the risk of doing or providing something.  COVID-19 may have contributed to, but it has not single-handedly created, uncertainty and risk. 

  • Jonathan Straw | Partner Kraftson & Caudle | Heavy Construction Law

Taxes Due!

March 10, 2020|

It’s tax season again, so it’s time to pay the piper.

  • Jonathan Straw | Partner Kraftson & Caudle | Heavy Construction Law

Claim Certified with Digital Signature Deemed OK

February 6, 2020|

The law is not a trend-setter.  It doesn’t readily change or adapt to tech.  So, a commonplace practice in business became a dispute when a claimant digitally certified a claim under the Contract Disputes Act.