When Massachusetts’ highest State court rejected Federal law on termination for convenience (T4C) a public entity’s “sole discretion . . . for any reason” ended a supplier’s contract. Is this too much governmental power or good stewardship of public resources?
Under a public contract, a Supplier agreed to provide fuel to the Massachusetts Bay Transportation Authority. About eleven months into the two-year contract, the Authority terminated the contract because it could get the same fuel for a cheaper price from a different supplier.
Upon 30-days written notice, termination by the Authority was within its “sole discretion . . . for any reason.” The terminated party was expressly entitled to payment for: demobilization, contract closeout, and costs of and profit on work performed.
The Massachusetts State Supreme Judicial Court held the termination was proper and made several points:
- Federal law on termination for convenience was not binding on the Commonwealth;
- General principles of contract interpretation under State law applied;
- The termination language was unambiguous and broad; and
- The requirement for pre-termination written notice was enough consideration for a contract.
The Court expressly stated it was not deciding whether a T4C would be proper to rebid the contract in search of a lower price. But, the roadmap of this decision would make it easy for a Court to find even such a T4C was OK.
Construction Contracting Without Relief Clauses During COVID-19
What to do if your contract lacks the parts to handle COVID-19? Considerations for creating new contracts during COVID-19.
Your Contract Can Handle COVID-19
Uncertainty and risk are not new or novel to contractors. Contracts reduce uncertainty and share the risk of doing or providing something. COVID-19 may have contributed to, but it has not single-handedly created, uncertainty and risk.
Contractors Can Use RFI to Notify the Government
The Board (and the government) should not elevate form over substance in evaluating the sufficiency of a contractor’s notice.
Taxes Due!
It’s tax season again, so it’s time to pay the piper.
Contractor Wins when Government Reconsiders Accord
Ever had buyer’s remorse or second-guessed a decision? When the U.S. Army Corps of Engineers did that, a Contractor won its claim […]
Claim Certified with Digital Signature Deemed OK
The law is not a trend-setter. It doesn’t readily change or adapt to tech. So, a commonplace practice in business became a dispute when a claimant digitally certified a claim under the Contract Disputes Act.
Acceptance and Intervening Cause Avoided Construction Warranty Claim
Like cars, computers, and appliances, construction projects include warranties too. Similarly, construction project warranties are limited to causes within the contractor’s control […]
Insurance Company Had No Duty to Defend Under Eight Corners Rule
To decide if an insurer has a duty to defend, a Virginia State or Federal Court may only look at the allegations in the complaint and the insurance policy to determine if a judgment against the insured will be covered by the policy.
Owner SOL When Mandatory Mediation Didn’t Toll Statute of Limitations
Contract interpretation strives to find the meaning of all parts together.