Contractors take heed – a time extension may be issued after substantial completion for specific work and the Government can still assess liquidated damages.
Under a contract with the U.S. Army Corps of Engineers, a Contractor agreed to construct facilities for support services, site logistics, and command in the Kingdom of Bahrain. The Government assessed LDs for delayed substantial completion. Several months later, after the Contractor had demobilized from the Project site, the Government issued an RFP for extra work. The Government accepted the Contractor’s pricing proposal for the extra work and established a deadline for completion of the same.
In its Certified Claim and on Appeal to the Armed Services Board of Contract Appeals, the Contractor unsuccessfully argued the award of extra work extended the overall deadline for substantial completion of the original scope of work. The bilateral Modification for the extra work provided in part, “This Period of Performance covers work under this modification only, not for the overall contract.”
The Board’s opinion doesn’t discuss what sort of extra work was performed. Presumably, the use or benefit of the overall Project did not depend upon completion of the extra work.
Roads & Bridges | Mediation Melee
MEDIATION MELEE| An arbitration case can be costly
Arbitration can be a bridge over troubled waters. In this crossing, the parties argued over […]
Roads & Bridges | Written Notice
WRITTEN NOTICE | Beware that strict compliance of the contract might be required.
When an owner replaced a contractor for significant safety violations, […]
Roads & Bridges | Mommie Dearest
MOMMY DEAREST | The story of an ESA without a MOM
Nobody enters this world, or a contract, without a mother: There can […]
IIJA | Does Closing a “Giant Loophole” Cost Contractors?
A recent article published by Roads and Bridges magazine reports that the Office of Management and Budget is working to broaden the scope […]
Roads & Bridges | Buy American Plan Gets an Update
BUY AMERICAN PLAN GETS AN UPDATE
The Office of Management and Budget is developing standards to replace the current Buy […]
Roads & Bridges
Where Does the Buck Stop?
WHERE DOES THE BUCK STOP? | A shallow concrete pour leads to an interesting lawsuit
On the desk of President Harry S. Truman […]
Roads & Bridges | Reshaping Agreements
RESHAPING AGREEMENTS | Oral Agreements Must Be Written in Stone
Reuse, reshaping, and/or reapplication of existing materials was the goal in this roadway […]
Pay-If-Paid Unenforceable in Virginia Starting Jan. 1, 2023
As of Jan. 1, 2023, pay-if-paid clauses are unenforceable, regardless of whether a surety/payment bond claim is involved. This is only for […]
How Short is Too Short
A limitations period is too short when it’s unreasonably short.