Virginia Federal Court upholds unilateral arbitration clause in construction contract.  On a Project for the United States Air Force at Langley Air Force Base in Hampton, Virginia, an electrical Subcontractor filed a lawsuit for nonpayment under the Federal Miller Act.  The clause provided that at Prime’s “sole election, any and all disputes . . . may be decided by mediation, arbitration or [ADR] proceedings as chosen by [Prime].”

The Court upheld the clause finding: (1) it was not vague simply because only one party (the Prime) could invoke its terms when the other party (Subcontractor) had already agreed to allow the Prime this right and (2) the contract as a whole was supported by sufficient consideration (i.e., benefit or detriment to each party).

This appears to be the first case by a Virginia court (state or federal) to interpret and uphold such a clause, which allowed only the Prime Contractor, not the Subcontractor, to resolve disputes by arbitration.  North Carolina, West Virginia, and now Virginia agree on upholding unilateral arbitration clauses.  Maryland disagrees.

When it’s time to butt heads, know how the local turf (court) will interpret the clause.

Head But Goats

U.S. f/u/b/o Harbor Construction Co., Inc. v. T.H.R. Enterprises, Inc., 311 F.Supp.3d 797 (U.S. District Ct., Eastern District of Virginia, April 26, 2018)

Published On: August 21, 2018

Share This Story, Choose Your Platform!

Linking Obligations

January 24, 2018|

If you want to bind the subcontractor to the prime in every way the same as the prime is bound to the owner, then the incorporation clause of the subcontract should be: . . .

Termination of Government Contracts for Convenience (T4C)

January 16, 2018|

Imagine you’re a Government Contractor under a firm, fixed-price contract and you’ve done nothing wrong.  Nevertheless, the Government has decided to unilaterally end its contract with you.  Yes, the Government can do this...

Government Contractors: Build a Snowman in August

January 8, 2018|

As a Government Contractor, when have you agreed to perform a certain way, but later realized that another way is better for everybody?  When the Government agrees, expressly or impliedly, to the alternative performance, it waives a credit for the unperformed work.

E-mail Signature Not Enough to Certify a Claim

December 5, 2017|

Construction project professionals routinely send e-mails with “signatures,” which typically include the sender’s typewritten name, title, contact information, and/or company logo.  But, this sort of e-mail “signature” is not enough to certify a claim to the Government.

Constructive Acceleration

November 14, 2017|

Contractors know that time is money.  So, the point is clear when expressly told to “Speed Up!  Go Faster!”

But, what do you […]

Construction Contracts & Whodunit

November 7, 2017|

Imagine reading a crime novel and just when you think you figured out whodunit, a plot twist suggests a different culprit. In construction contracting, finding the right answer can be a difficult task when