If all apples are fruit, then why are all fruit not apples? Because the part does not represent the whole. A Government Contractor discovered this when it learned that all unsuitable material was unsatisfactory material; but, all unsatisfactory material was not unsuitable material. Let me explain . . .
Under a Contract with the U.S. Army Corps of Engineers for two explosives storage magazines and a storm drain at Picatinny Arsenal, New Jersey, “unsatisfactory materials” were to be replaced with satisfactory materials. Basically, “unsatisfactory materials” included anything that could not be used as backfill.
As is typical, the Corps answered several pre-bid questions that later became amendments to the Contract. One of the Corps’ answers stated, “assume unsuitable material is not encountered.” The Contractor improperly equated “unsuitable material” with “unsatisfactory material.”
Although the term “unsuitable material” was not separately defined in the Contract, the Court found that other Contract provisions (e.g., pre-bid Q&A’s, specs, and soil borings) helped to define it as “unsatisfactory material” but only at certain depths/locations. Thus, the pre-bid Q&A did not pertain to “unsatisfactory materials” generally; but, only a subset of unsatisfactory materials – “unsuitable materials.”
While the whole included the part (unsatisfactory material included all unsuitable material), the part did not equal the whole (unsuitable material did not include all unsatisfactory material).
Construction Dispute Settlement: Dealing with Details
Reap the benefits of settling a construction dispute by doing these things.
E-mail Signature Not Enough to Certify a Claim
Construction project professionals routinely send e-mails with “signatures,” which typically include the sender’s typewritten name, title, contact information, and/or company logo. But, this sort of e-mail “signature” is not enough to certify a claim to the Government.
Government Contractors: Ask for a “Sum Certain” in Your Claim
If your Claim includes an item for damages with an amount “TBD,” you could lose the entire Claim.
Contractors: Be Aware When Contracting with Virginia Public Agencies
Without a valid contract, a Virginia public entity has no duty to to pay for any of your work.
Constructive Acceleration
Contractors know that time is money. So, the point is clear when expressly told to “Speed Up! Go Faster!”
But, what do you […]
Construction Contracts & Whodunit
Imagine reading a crime novel and just when you think you figured out whodunit, a plot twist suggests a different culprit. In construction contracting, finding the right answer can be a difficult task when
Trick or Treat in Government Contract Claims
Without a request for a contracting officer’s final decision, claimants may seek treats, but get tricked instead.
Owner Nonpayment is No Defense to Miller Act Claim
As if you needed confirmation that the Federal Miller Act is a powerful tool for unpaid subcontractors, this is it. Even when a Prime ordered and accepted the Sub’s work, but didn’t have to pay under the Subcontract, the Subcontractor still. . . .
Trust, but Verify
Rely at your own risk upon a Contracting Officer’s statements when statutes or contract provisions may conflict.