If all apples are fruit, then why are all fruit not apples?  Because the part does not represent the whole.  A Government Contractor discovered this when it learned that all unsuitable material was unsatisfactory material; but, all unsatisfactory material was not unsuitable material.  Let me explain . . .

Under a Contract with the U.S. Army Corps of Engineers for two explosives storage magazines and a storm drain at Picatinny Arsenal, New Jersey, “unsatisfactory materials” were to be replaced with satisfactory materials.  Basically, “unsatisfactory materials” included anything that could not be used as backfill.

As is typical, the Corps answered several pre-bid questions that later became amendments to the Contract.  One of the Corps’ answers stated, “assume unsuitable material is not encountered.”  The Contractor improperly equated “unsuitable material” with “unsatisfactory material.”

Although the term “unsuitable material” was not separately defined in the Contract, the Court found that other Contract provisions (e.g., pre-bid Q&A’s, specs, and soil borings) helped to define it as “unsatisfactory material” but only at certain depths/locations.  Thus, the pre-bid Q&A did not pertain to “unsatisfactory materials” generally; but, only a subset of unsatisfactory materials – “unsuitable materials.”

While the whole included the part (unsatisfactory material included all unsuitable material), the part did not equal the whole (unsuitable material did not include all unsatisfactory material).

Senate Builders and Construction Managers, Inc. v. U.S., Ct. of Fed. Claims, Case No. 14-1196C (April 29, 2017).

Published On: March 8, 2018

Share This Story, Choose Your Platform!

E-mail Signature Not Enough to Certify a Claim

December 5, 2017|

Construction project professionals routinely send e-mails with “signatures,” which typically include the sender’s typewritten name, title, contact information, and/or company logo.  But, this sort of e-mail “signature” is not enough to certify a claim to the Government.

Constructive Acceleration

November 14, 2017|

Contractors know that time is money.  So, the point is clear when expressly told to “Speed Up!  Go Faster!”

But, what do you […]

Construction Contracts & Whodunit

November 7, 2017|

Imagine reading a crime novel and just when you think you figured out whodunit, a plot twist suggests a different culprit. In construction contracting, finding the right answer can be a difficult task when

Owner Nonpayment is No Defense to Miller Act Claim

October 24, 2017|

As if you needed confirmation that the Federal Miller Act is a powerful tool for unpaid subcontractors, this is it.  Even when a Prime ordered and accepted the Sub’s work, but didn’t have to pay under the Subcontract, the Subcontractor still. . . .

Trust, but Verify

October 17, 2017|

Rely at your own risk upon a Contracting Officer’s statements when statutes or contract provisions may conflict.

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!