Since Y2K, sureties for federal projects in Virginia have been unable to defend against bond lawsuits by asserting pay-if-paid or pay-when paid clauses. Now, sureties are also unable to rely upon no-damage-for-delay (ND4D) and owner-related disputes clauses.
Recently, the Federal District Court for the Eastern District of Virginia held that a Prime’s Surety could not use the ND4D clause to defend against a Sub’s Miller Act lawsuit. Neither was the Sub required to wait until resolution of delays that the Owner may have caused, despite an express subcontract provision requiring as much.
The Court held that “the subcontract cannot eliminate the right to payment altogether, or delay it, unless the subcontract does so in a manner consistent with the terms of the Miller Act.” The only consistent means of which this author knows, and which the Court endorsed, were interim payment waivers for work already performed. The Court likened ND4D clauses to prospective waivers, which the Court said are prohibited by the Miller Act (although no such language exists in the Act).
E-mail Signature Not Enough to Certify a Claim
Construction project professionals routinely send e-mails with “signatures,” which typically include the sender’s typewritten name, title, contact information, and/or company logo. But, this sort of e-mail “signature” is not enough to certify a claim to the Government.
Government Contractors: Ask for a “Sum Certain” in Your Claim
If your Claim includes an item for damages with an amount “TBD,” you could lose the entire Claim.
Contractors: Be Aware When Contracting with Virginia Public Agencies
Without a valid contract, a Virginia public entity has no duty to to pay for any of your work.
Constructive Acceleration
Contractors know that time is money. So, the point is clear when expressly told to “Speed Up! Go Faster!”
But, what do you […]
Construction Contracts & Whodunit
Imagine reading a crime novel and just when you think you figured out whodunit, a plot twist suggests a different culprit. In construction contracting, finding the right answer can be a difficult task when
Trick or Treat in Government Contract Claims
Without a request for a contracting officer’s final decision, claimants may seek treats, but get tricked instead.
Owner Nonpayment is No Defense to Miller Act Claim
As if you needed confirmation that the Federal Miller Act is a powerful tool for unpaid subcontractors, this is it. Even when a Prime ordered and accepted the Sub’s work, but didn’t have to pay under the Subcontract, the Subcontractor still. . . .
Trust, but Verify
Rely at your own risk upon a Contracting Officer’s statements when statutes or contract provisions may conflict.
Payment for Verbal Changes When a Writing was “Required”
Even if your agreement can only be modified by a writing, you may still have a good argument to be paid for extra work.










