During a recent soccer game, my seven-year-old son took the ball squarely in the face.  But, he walked it off and continued playing.  Contractors must do the same with changes.

In 2006, under a contract with NAVFAC for repairs to a wastewater treatment system at Naval Station Guantanamo Bay Cuba, the Contractor encountered differing site conditions.  NAVFAC did not issue a suspension or stop work order, but the Contractor stopped working awaiting responses to RFIs.  NAVFAC did not respond to all the RFIs.  So, the Contractor submitted a certified claim, but the Contractor never resumed work.  The Contractor should have continued working.

Under the Federal Acquisition Regulations, the Contractor is obligated to “prosecute the work diligently” and continue performance pending the outcome of a claim. (FAR 52.211-10 and 52.233-1(i)).  Doing so not only mitigates potential delays and damages, but it ensures that when a claim is submitted, a “sum certain” (i.e., showing of damage) is possible.

In this case, the Contractor’s claim submission was premature and the Contractor’s refusal to perform directed or constructive changes pending the promise of payment precluded the ASBCA from having any power to resolve the dispute.  The ASBCA dismissed the Contractor’s appeal because the Contractor sought future damages for work it had not yet performed.  At worst, NAVFAC could have terminated the Contractor for default.

Appeal of Islands Mechanical Contractor, Inc., ASBCA No. 59655 (April 13, 2017)

Published On: May 15, 2017

Share This Story, Choose Your Platform!

  • Your Contract Can Handle COVID-19

Your Contract Can Handle COVID-19

April 9, 2020|

Uncertainty and risk are not new or novel to contractors.  Contracts reduce uncertainty and share the risk of doing or providing something.  COVID-19 may have contributed to, but it has not single-handedly created, uncertainty and risk. 

  • Jonathan Straw | Partner Kraftson & Caudle | Heavy Construction Law

Taxes Due!

March 10, 2020|

It’s tax season again, so it’s time to pay the piper.

  • Jonathan Straw | Partner Kraftson & Caudle | Heavy Construction Law

Claim Certified with Digital Signature Deemed OK

February 6, 2020|

The law is not a trend-setter.  It doesn’t readily change or adapt to tech.  So, a commonplace practice in business became a dispute when a claimant digitally certified a claim under the Contract Disputes Act.

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!