Despite “abhorrent” behavior by the Army Corps of Engineers, a majority of the Armed Services Board of Contract Appeals held there was no breach of the duty of good faith and fair dealing. Yet, the Contractor recovered almost all of its claimed damages because the Corps forced the Contractor to sign a modification under duress and ignored a significant constructive change.
In this story, two bids were submitted for maintenance dredging of the Scarborough River, Scarborough, Maine. The successful bidder was 40% lower than the Government’s initial estimate. Before contract award the Corps requested a change to the winning bidder’s plan at no additional cost to the Government and the Corps revised its Government estimate to be only 14% higher than the winning bid.
After award, the Corps unilaterally reduced the amounts it had agreed to pay for certain CLINs, which effectively cut off the contractor’s cash flow for the Project.
From these facts, a minority of the Board found the Corps breached its duty of good faith and fair dealing. However, a majority of the Board held there was no breach, despite the Corps’ “abhorrent” and unreasonable behavior. (A split of opinion on the Board is rare.)
The full opinion has more detail of how unfairly the Corps treated the Contractor.
Appeals of North American Landscaping, Construction, and Dredge, Co., Inc., Armed Services Board of Contract Appeals Nos. 60235, 60236, 60237, and 60238 (August 9, 2018).
Roads & Bridges | Maximizing Damage Recovery
MAXIMIZING DAMAGE RECOVERY
Tracking Costs, Avoiding Duplication in Liquidated and Actual Damage Claims
A County and Contractor contracted for construction of a road and […]
Roads & Bridges | Roadwork, Delays and Disputes
ROADWORK, DELAYS, AND DISPUTES
The Subcontract Case In Pecos County, Texas
“Road construction is ubiquitous in our society. . . .” C&C Road […]
Roads & Bridges | Understanding Sovereign Immunity
UNDERSTANDING SOVEREIGN IMMUNITY| Public Contracts and Lessons from Recent Texas Cases
Generally, governmental entities are immune from lawsuits. One exception is contractual. If […]
Roads & Bridges | Indiana Court Upholds Broad ND4D Clause
INDIANA COURT UPHOLDS BROAD ND4D CLAUSE | Ruling Precludes Subcontractor Claims for Delay and Acceleration Damages
This is the story of an Indiana […]
Roads & Bridges | Some Conditions Apply
SOME CONDITIONS APPLY | The scope of insurance policy coverage and what the terms dictate
At some time or another, many have tried […]
Roads & Bridges | Contract Termination
CONTRACT TERMINATION | An unpredictable case teaches hard lessons to each party involved
Court decisions are “opinions.” There are majority and dissenting (disagreeing) […]
Roads & Bridges | Good Faith and Fair Dealing
GOOD FAITH AND FAIR DEALING | How Do You Prove a Party Has Failed to Act Based Upon an Ulterior Motive?
The duty […]
Roads & Bridges | Not Another Notice Story
NOT ANOTHER NOTICE STORY| This Defensive Argument Seems to be on the Rise
AS I CONSIDERED the subject matter for this column, I […]
Roads & Bridges | All According to Plan
ALL ACCORDING TO PLAN | Exact Measurements Go a Long Way
In December 2013, a contractor agreed to replace four bridges for the […]