Requirements may exist outside the four corners of the contract when such requirements are: (1) otherwise mandatory and (2) express a significant or deeply ingrained strand of public procurement policy. In other words, your contract may include requirements not shown or otherwise indicated in the contract documents.
In an example of this, a Contractor agreed to provide pre-engineered metal buildings for the Army’s use at Camp Edwards, Massachusetts. Under the Miller Act and the FAR, bonds for construction projects are mandatory. The mandate for payment bonds is based upon the “deeply ingrained strand of public procurement policy” that security should be provided for entities or persons furnishing labor and materials in the performance of government contracts. The mandate for performance bonds is due to the Government’s need for security to ensure the use of public funds results in a finished product since not completing a public project could be a waste or misuse of public funds. Of course, (dripping with sarcasm) we’ve never seen a public entity waste or misuse public funds, right.
The Armed Services Board of Contract Appeals held bonds were part of the contract even though bonding requirements were not expressly stated nor incorporated by reference. The U.S. Court of Appeals for the Federal Circuit agreed with the Board. K-Con, Inc. v. Secretary of the Army, U.S. Court of Appeals for the Federal Circuit, Case No.: 2017-2254 (Nov. 5, 2018).
Next time you review an RFP, carefully consider what you don’t see but that may still be required.
Read another short example here: Adding Terms to a Government Contract without Saying So.
Roads & Bridges | Not Another Notice Story
NOT ANOTHER NOTICE STORY| This Defensive Argument Seems to be on the Rise
AS I CONSIDERED the subject matter for this column, I […]
Roads & Bridges | All According to Plan
ALL ACCORDING TO PLAN | Exact Measurements Go a Long Way
In December 2013, a contractor agreed to replace four bridges for the […]
Roads & Bridges | Connecting the Dots
CONNECTING THE DOTS | Showing Causation in Contracting Cases is Critical
In this asphalt case, the prime contractor agreed to perform a $13 […]
Roads & Bridges | Liquidated Damages
LIQUIDATED DAMAGES | Penalties and What is Unenforceable
Liquidated damages typically flow from delays, but they are not always solidly enforced.
In June 2017, […]
Roads& Bridges | Warranty Provisions
WARRANTY PROVISIONS | Contracts must be interpreted thoroughly to avoid absurd results
You are responsible for things within your control. Be careful if […]
Roads& Bridges | The Agreed Price
THE AGREED PRICE | This case stands as a warning about pay-if-paid clause
History cannot be rewritten and a bad, but legal, […]
Roads& Bridges | Confusing Waters
CONFUSING WATERS | A Supreme Court ruling leaves room for ambiguity
What happens when there may be a “significant nexus” between “adjacent” and/or […]
Roads & Bridges | Authority Defined
AUTHORITY DEFINED | The Law of Agency is Important to Understand
For any project, this Russian proverb is helpful: Doveryay, no proveryay – […]
Jurisdiction is Power
Not bad power, but the ability of a decision-maker (e.g., court) to decide which side is right (or which is more correct). […]