When you know a current action or inaction is wrong, but you do not object, should you be allowed to object later? Typical notions of fairness may suggest the answer is no. But, contractual fairness is whatever the parties’ agreed would be fair before the wrong action or inaction ever occurred.
In September 2009, a Contractor agreed to perform reconstruction work on a hurricane protection levee in St. Charles Parish, Louisiana. The Contract included specific requirements for the placement of geotextile fabric. With the U.S. Army Corps of Engineers inspectors onsite and observing, the Contractor installed (or placed) most of the total fabric for the Project. The Contractor also submitted QC reports detailing how the fabric was placed. The Corps acknowledged receipt of the Contractor’s QC reports and took no exceptions to the Contractor’s methodology.
Only after the Project was about 2/3 complete, did the Corps reject the Contractor’s placement methodology as being contrary to the Contract requirements. The Corps demanded all the fabric that was already placed and covered with fill be uncovered and re-placed. The Contractor understandably objected, but had to comply and filed a certified claim seeking recovery.
The Armed Services Board of Contract Appeals held the Contract requirements were not ambiguous (i.e., the Contractor should have known it was placing the fabric incorrectly).
The Contractor is in a tough spot. It thought that its interpretation of the Contract was reasonable and correct. So, the Contractor thought it was unnecessary to formally confirm its understanding with the Corps before beginning work. Additionally, the Contractor probably thought its understanding was confirmed when the Corps inspectors did not object.
This story is not over. The Contractor may yet prevail at a hearing. The text of the fabric placement requirements is included in the link below. Do you think it’s unclear?

Roads & Bridges | Court Defines When Contractors Can Withdraw Due to Mistakes
BIDDING BLUNDER
Roads & Bridges | Court Defines When Contractors Can Withdraw Due to Mistakes
For over 125 years, the vast majority of jurisdictions […]
FEDERAL CONTRACT TERMINATION OR MODIFICATION
The White House has directed Agency heads to “terminate or modify . . . covered contracts.” With some exceptions, there are […]
Roads & Bridges | Maximizing Damage Recovery
MAXIMIZING DAMAGE RECOVERY
Tracking Costs, Avoiding Duplication in Liquidated and Actual Damage Claims
A County and Contractor contracted for construction of a road and […]
Roads & Bridges | Roadwork, Delays and Disputes
ROADWORK, DELAYS, AND DISPUTES
The Subcontract Case In Pecos County, Texas
“Road construction is ubiquitous in our society. . . .” C&C Road […]
Roads & Bridges | Understanding Sovereign Immunity
UNDERSTANDING SOVEREIGN IMMUNITY| Public Contracts and Lessons from Recent Texas Cases
Generally, governmental entities are immune from lawsuits. One exception is contractual. If […]
Roads & Bridges | Indiana Court Upholds Broad ND4D Clause
INDIANA COURT UPHOLDS BROAD ND4D CLAUSE | Ruling Precludes Subcontractor Claims for Delay and Acceleration Damages
This is the story of an Indiana […]
Roads & Bridges | Some Conditions Apply
SOME CONDITIONS APPLY | The scope of insurance policy coverage and what the terms dictate
At some time or another, many have tried […]
Roads & Bridges | Contract Termination
CONTRACT TERMINATION | An unpredictable case teaches hard lessons to each party involved
Court decisions are “opinions.” There are majority and dissenting (disagreeing) […]
Roads & Bridges | Good Faith and Fair Dealing
GOOD FAITH AND FAIR DEALING | How Do You Prove a Party Has Failed to Act Based Upon an Ulterior Motive?
The duty […]