When you know a current action or inaction is wrong, but you do not object, should you be allowed to object later? Typical notions of fairness may suggest the answer is no. But, contractual fairness is whatever the parties’ agreed would be fair before the wrong action or inaction ever occurred.
In September 2009, a Contractor agreed to perform reconstruction work on a hurricane protection levee in St. Charles Parish, Louisiana. The Contract included specific requirements for the placement of geotextile fabric. With the U.S. Army Corps of Engineers inspectors onsite and observing, the Contractor installed (or placed) most of the total fabric for the Project. The Contractor also submitted QC reports detailing how the fabric was placed. The Corps acknowledged receipt of the Contractor’s QC reports and took no exceptions to the Contractor’s methodology.
Only after the Project was about 2/3 complete, did the Corps reject the Contractor’s placement methodology as being contrary to the Contract requirements. The Corps demanded all the fabric that was already placed and covered with fill be uncovered and re-placed. The Contractor understandably objected, but had to comply and filed a certified claim seeking recovery.
The Armed Services Board of Contract Appeals held the Contract requirements were not ambiguous (i.e., the Contractor should have known it was placing the fabric incorrectly).
The Contractor is in a tough spot. It thought that its interpretation of the Contract was reasonable and correct. So, the Contractor thought it was unnecessary to formally confirm its understanding with the Corps before beginning work. Additionally, the Contractor probably thought its understanding was confirmed when the Corps inspectors did not object.
This story is not over. The Contractor may yet prevail at a hearing. The text of the fabric placement requirements is included in the link below. Do you think it’s unclear?

Roads & Bridges | Award Upheld in W. Va. Caisson Dispute
AWARD UPHELD IN W.VA. CAISSON DISPUTE
Federal court reinforces high bar for overturning arbitration
In 2018, the West Virginia Department of Highways (DOH) awarded […]
Roads & Bridges |Let the Contract Lead
LET THE CONTRACT LEAD
Documents offer guidance needed to manage risk without derailing projects
Construction is an industry of managed risk. Whether the prices […]
Roads & Bridges | When is an Invoice Really an Invoice?
WHEN IS AN INVOICE REALLY AN INVOICE?
All court decisions are opinions. Appellate court decisions are typically made by a panel of three […]
Roads & Bridges | Clarifying Punitive Damages
CLARIFYING PUNITIVE DAMAGES
In June 2021, the South Dakota Department of Transportation contracted for the demolition and construction of a bridge on State […]
Roads & Bridges | When Approximate Means Assumed Risk
WHEN APPROXIMATE MEANS ASSUMED RISK
A New York Court Shows How Performance Specifications Can Leave Contractors Holding the Bag
Sometimes when we are told […]
Roads & Bridges | From Roman Arches to AI
FROM ROMAN ARCHES TO AI
Can Construction Evolve Without Risk?
The construction industry blends old with new. From ancient Roman archways and aqueducts and […]
Roads & Bridges | Caught in the Middle
CAUGHT IN THE MIDDLE
New Mexico bridge case highlights the importance of written agreements for changes and delay compensation
In construction contracting, hope for […]
Roads & Bridges | Wait and It’s Waived
WAIT AND IT’S WAIVED
Roads & Bridges | Supreme Court Ruling on Arbitration Delay
Don’t wait to arbitrate! Progressing too far down the litigation […]
Roads & Bridges | Court Defines When Contractors Can Withdraw Due to Mistakes
BIDDING BLUNDER
Roads & Bridges | Court Defines When Contractors Can Withdraw Due to Mistakes
For over 125 years, the vast majority of jurisdictions […]










