What to do when the drawings indicate one thing while the specifications require something different?

On a federal construction project, the specifications trump the drawings. (Federal Acquisition Regulations 52.236-21(a)).  But, remember these things too:

  1. Always ask sooner rather than later about obvious differences.
  2. If the difference is patent (i.e., apparent on its face) and you haven’t submitted a bid yet, then pose the question or risk misinterpreting.
  3. If the difference is latent (i.e., not apparent on its face, but only upon learning additional information and capable of more than one reasonable interpretation), then you probably won’t (and hopefully can’t) discover it until after contract award.

In any event, you should promptly notify the Contracting Officer and Designer of Record upon discovery of any discrepancies.

Eggs

Published On: February 7, 2018

Share This Story, Choose Your Platform!

Roads & Bridges | Liquidated Damages

February 24, 2024|

LIQUIDATED DAMAGES | Penalties and What is Unenforceable

Liquidated damages typically flow from delays, but they are not always solidly enforced.

In June 2017, […]

  • Roads & Bridges | Warranty Provisions

Roads& Bridges | Warranty Provisions

January 25, 2024|

WARRANTY PROVISIONS | Contracts must be interpreted thoroughly to avoid absurd results

You are responsible for things within your control. Be careful if […]

Roads& Bridges | Confusing Waters

October 17, 2023|

CONFUSING WATERS | A Supreme Court ruling leaves room for ambiguity

What happens when there may be a “significant nexus” between “adjacent” and/or […]

  • Sum Certain Blog Post

Jurisdiction is Power

August 27, 2023|

Not bad power, but the ability of a decision-maker (e.g., court) to decide which side is right (or which is more correct). […]

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!