What to do when the drawings indicate one thing while the specifications require something different?
On a federal construction project, the specifications trump the drawings. (Federal Acquisition Regulations 52.236-21(a)). But, remember these things too:
- Always ask sooner rather than later about obvious differences.
- If the difference is patent (i.e., apparent on its face) and you haven’t submitted a bid yet, then pose the question or risk misinterpreting.
- If the difference is latent (i.e., not apparent on its face, but only upon learning additional information and capable of more than one reasonable interpretation), then you probably won’t (and hopefully can’t) discover it until after contract award.
In any event, you should promptly notify the Contracting Officer and Designer of Record upon discovery of any discrepancies.

Roads & Bridges | Some Conditions Apply
SOME CONDITIONS APPLY | The scope of insurance policy coverage and what the terms dictate
At some time or another, many have tried […]
Roads & Bridges | Contract Termination
CONTRACT TERMINATION | An unpredictable case teaches hard lessons to each party involved
Court decisions are “opinions.” There are majority and dissenting (disagreeing) […]
Roads & Bridges | Good Faith and Fair Dealing
GOOD FAITH AND FAIR DEALING | How Do You Prove a Party Has Failed to Act Based Upon an Ulterior Motive?
The duty […]
Roads & Bridges | Not Another Notice Story
NOT ANOTHER NOTICE STORY| This Defensive Argument Seems to be on the Rise
AS I CONSIDERED the subject matter for this column, I […]
Roads & Bridges | All According to Plan
ALL ACCORDING TO PLAN | Exact Measurements Go a Long Way
In December 2013, a contractor agreed to replace four bridges for the […]
Roads & Bridges | Connecting the Dots
CONNECTING THE DOTS | Showing Causation in Contracting Cases is Critical
In this asphalt case, the prime contractor agreed to perform a $13 […]
Roads & Bridges | Liquidated Damages
LIQUIDATED DAMAGES | Penalties and What is Unenforceable
Liquidated damages typically flow from delays, but they are not always solidly enforced.
In June 2017, […]
Roads& Bridges | Warranty Provisions
WARRANTY PROVISIONS | Contracts must be interpreted thoroughly to avoid absurd results
You are responsible for things within your control. Be careful if […]
Roads& Bridges | The Agreed Price
THE AGREED PRICE | This case stands as a warning about pay-if-paid clause
History cannot be rewritten and a bad, but legal, […]