What to do when the drawings indicate one thing while the specifications require something different?
On a federal construction project, the specifications trump the drawings. (Federal Acquisition Regulations 52.236-21(a)). But, remember these things too:
- Always ask sooner rather than later about obvious differences.
- If the difference is patent (i.e., apparent on its face) and you haven’t submitted a bid yet, then pose the question or risk misinterpreting.
- If the difference is latent (i.e., not apparent on its face, but only upon learning additional information and capable of more than one reasonable interpretation), then you probably won’t (and hopefully can’t) discover it until after contract award.
In any event, you should promptly notify the Contracting Officer and Designer of Record upon discovery of any discrepancies.

FEDERAL CONTRACT TERMINATION OR MODIFICATION
The White House has directed Agency heads to “terminate or modify . . . covered contracts.” With some exceptions, there are […]
Roads & Bridges | Maximizing Damage Recovery
MAXIMIZING DAMAGE RECOVERY
Tracking Costs, Avoiding Duplication in Liquidated and Actual Damage Claims
A County and Contractor contracted for construction of a road and […]
Roads & Bridges | Roadwork, Delays and Disputes
ROADWORK, DELAYS, AND DISPUTES
The Subcontract Case In Pecos County, Texas
“Road construction is ubiquitous in our society. . . .” C&C Road […]
Roads & Bridges | Understanding Sovereign Immunity
UNDERSTANDING SOVEREIGN IMMUNITY| Public Contracts and Lessons from Recent Texas Cases
Generally, governmental entities are immune from lawsuits. One exception is contractual. If […]
Roads & Bridges | Indiana Court Upholds Broad ND4D Clause
INDIANA COURT UPHOLDS BROAD ND4D CLAUSE | Ruling Precludes Subcontractor Claims for Delay and Acceleration Damages
This is the story of an Indiana […]
Roads & Bridges | Some Conditions Apply
SOME CONDITIONS APPLY | The scope of insurance policy coverage and what the terms dictate
At some time or another, many have tried […]
Roads & Bridges | Contract Termination
CONTRACT TERMINATION | An unpredictable case teaches hard lessons to each party involved
Court decisions are “opinions.” There are majority and dissenting (disagreeing) […]
Roads & Bridges | Good Faith and Fair Dealing
GOOD FAITH AND FAIR DEALING | How Do You Prove a Party Has Failed to Act Based Upon an Ulterior Motive?
The duty […]
Roads & Bridges | Not Another Notice Story
NOT ANOTHER NOTICE STORY| This Defensive Argument Seems to be on the Rise
AS I CONSIDERED the subject matter for this column, I […]