CAUGHT IN THE MIDDLE
New Mexico bridge case highlights the importance of written agreements for changes and delay compensation

In construction contracting, hope for (and focus on) the best after planning for the worst.

In 2018, the New Mexico Department of Transportation (NMDOT) selected a prime contractor for construction of a bridge in Quay County, N.M. (The eastern border of Quay County is also the New Mexico/Texas border). The prime subcontracted for cast-in-place piers and other bridge components. NMDOT and the prime entered into a change order to alter the pier design, which increased the quantity of work and delayed the project. Continue reading.

Published On: August 26, 2025

Share This Story, Choose Your Platform!

  • A Supreme Court ruling leaves room for ambiguity

Roads & Bridges | Mediation Melee

June 13, 2023|

MEDIATION MELEE| An arbitration case can be costly

Arbitration can be a bridge over troubled waters. In this crossing, the parties argued over […]

  • Written Notice | Roads & Bridges Article | Jon Straw

Roads & Bridges | Written Notice

April 2, 2023|

WRITTEN NOTICE | Beware that strict compliance of the contract might be required.

When an owner replaced a contractor for significant safety violations, […]

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!