The White House has directed Agency heads to “terminate or modify . . . covered contracts.” With some exceptions, there are numerous potential contracts on the chopping block. What should contractors do?
Upon receipt of a unilateral modification, assess whether the cost or time will increase in unchanged areas. For example, deductive changes for certain work could increase costs for other work that must still be performed. If costs were increased because of deductive changes, then carefully consider submitting a request for equitable adjustment.
Upon receipt of a notice of complete termination for convenience, promptly stop incurring further costs and, within one year of the termination, present a reasonable and well-supported termination settlement proposal to the Government under FAR 52.249-2(e). Recoverable costs include:
1. Costs actually incurred;
2. Profit on the work actually done; and
3. Costs of preparing a termination settlement proposal.
Upon receipt of a notice of partial termination for convenience, promptly stop incurring costs related to the terminated portion of the work and present a request for equitable adjustment within 90 days of the notice under FAR 52.249-2(l).
HEADER PHOTO: Termination by Nick Youngson CC BY-SA 3.0 Alpha Stock Images
Roads & Bridges |Let the Contract Lead
LET THE CONTRACT LEAD
Documents offer guidance needed to manage risk without derailing projects
Construction is an industry of managed risk. Whether the prices […]
Roads & Bridges | When is an Invoice Really an Invoice?
WHEN IS AN INVOICE REALLY AN INVOICE?
All court decisions are opinions. Appellate court decisions are typically made by a panel of three […]
Roads & Bridges | Clarifying Punitive Damages
CLARIFYING PUNITIVE DAMAGES
In June 2021, the South Dakota Department of Transportation contracted for the demolition and construction of a bridge on State […]
Roads & Bridges | When Approximate Means Assumed Risk
WHEN APPROXIMATE MEANS ASSUMED RISK
A New York Court Shows How Performance Specifications Can Leave Contractors Holding the Bag
Sometimes when we are told […]
Roads & Bridges | From Roman Arches to AI
FROM ROMAN ARCHES TO AI
Can Construction Evolve Without Risk?
The construction industry blends old with new. From ancient Roman archways and aqueducts and […]
Roads & Bridges | Caught in the Middle
CAUGHT IN THE MIDDLE
New Mexico bridge case highlights the importance of written agreements for changes and delay compensation
In construction contracting, hope for […]
Roads & Bridges | Wait and It’s Waived
WAIT AND IT’S WAIVED
Roads & Bridges | Supreme Court Ruling on Arbitration Delay
Don’t wait to arbitrate! Progressing too far down the litigation […]
Roads & Bridges | Court Defines When Contractors Can Withdraw Due to Mistakes
BIDDING BLUNDER
Roads & Bridges | Court Defines When Contractors Can Withdraw Due to Mistakes
For over 125 years, the vast majority of jurisdictions […]
FEDERAL CONTRACT TERMINATION OR MODIFICATION
The White House has directed Agency heads to “terminate or modify . . . covered contracts.” With some exceptions, there are […]