GOOD FAITH AND FAIR DEALING | How Do You Prove a Party Has Failed to Act Based Upon an Ulterior Motive?

The duty of good faith and fair dealing comes with every contract. A breach of which is challenging to prove because it is relatively simple to fulfill.

In 2017, a contractor agreed to mill and overlay a 36-mile segment of State Highway 59 for the Minnesota Department of Transportation (MnDOT) with a successful bid of about $9.8 million.

Continue reading…

 

 

Published On: August 12, 2024

Share This Story, Choose Your Platform!

Roads & Bridges | Liquidated Damages

February 24, 2024|

LIQUIDATED DAMAGES | Penalties and What is Unenforceable

Liquidated damages typically flow from delays, but they are not always solidly enforced.

In June 2017, […]

  • Roads & Bridges | Warranty Provisions

Roads& Bridges | Warranty Provisions

January 25, 2024|

WARRANTY PROVISIONS | Contracts must be interpreted thoroughly to avoid absurd results

You are responsible for things within your control. Be careful if […]

Roads& Bridges | Confusing Waters

October 17, 2023|

CONFUSING WATERS | A Supreme Court ruling leaves room for ambiguity

What happens when there may be a “significant nexus” between “adjacent” and/or […]

  • Sum Certain Blog Post

Jurisdiction is Power

August 27, 2023|

Not bad power, but the ability of a decision-maker (e.g., court) to decide which side is right (or which is more correct). […]