WARRANTY PROVISIONS | Contracts must be interpreted thoroughly to avoid absurd results

You are responsible for things within your control. Be careful if assuming responsibility without control.

On a public works contract for a public owner in Washington, the contractor constructed and installed a pipeline to convey overflow wastewater toward a diversion structure and storage tank. Nine months after substantial completion, the owner discovered the pipeline had fractured, allowing soil and other debris into the pipe.

Continue reading…

 

 

Published On: January 25, 2024

Share This Story, Choose Your Platform!

  • An Unpredictable Case Teaches Hard Lessons | Contract Termination

Roads & Bridges | Contract Termination

September 9, 2024|

CONTRACT TERMINATION | An unpredictable case teaches hard lessons to each party involved

Court decisions are “opinions.” There are majority and dissenting (disagreeing) […]

Share This Story, Choose Your Platform!

Jonathan J. Straw
Best Lawyers® - Jonathan Straw | 2026

Share This Story, Choose Your Platform!