Too often I’ve heard, “we didn’t want to rock the boat, so we just discussed the problem, but didn’t provide written notice.” But, remember The Godfather – “It’s not personal, it’s strictly business.”
Under a contract to furnish and install HVAC piping for a U.S. Army training facility at Joint Base Elmendorf-Richardson in Anchorage, Alaska, the Contractor argued the contract drawings and specs lacked the design details necessary to perform the work. The Contractor submitted several RFIs.
The Government argued the Contractor must use a letter, not an RFI, to notify the Contracting Officer of design problems. The Board held the information conveyed in the Contractor’s RFIs was sufficient to notify the government of a design discrepancy and “the Board (and the government) should not elevate form over substance in evaluating the sufficiency of a contractor’s notice.”
The Government also argued that the Contractor bore the risk of performing the changed work before the CO responded to the Contractor’s notice. Holding in the Contractor’s favor, the Board reasoned the risk borne by the Contractor is the risk of an incorrect course of action. If the Contractor takes the correct course of action (i.e., if it performs the work exactly as the CO would have directed) the Government suffers no harm, so the Contractor bears no such risk. When the Contractor acts before the CO responds, the Contractor bears the risk of taking incorrect action. If you’re gonna act, make it the correct action.
This case did not decide which party was at fault for the missing design details (i.e., Spearin Doctrine). But, [spoiler alert] the Government doesn’t automatically bear such responsibility even if it is a design-bid-build contract.
Appeal of UNIT Company, Armed Services Board of Contract Appeals, No. 60581 (Feb. 12, 2018).
Roads & Bridges |Let the Contract Lead
LET THE CONTRACT LEAD
Documents offer guidance needed to manage risk without derailing projects
Construction is an industry of managed risk. Whether the prices […]
Roads & Bridges | When is an Invoice Really an Invoice?
WHEN IS AN INVOICE REALLY AN INVOICE?
All court decisions are opinions. Appellate court decisions are typically made by a panel of three […]
Roads & Bridges | Clarifying Punitive Damages
CLARIFYING PUNITIVE DAMAGES
In June 2021, the South Dakota Department of Transportation contracted for the demolition and construction of a bridge on State […]
Roads & Bridges | When Approximate Means Assumed Risk
WHEN APPROXIMATE MEANS ASSUMED RISK
A New York Court Shows How Performance Specifications Can Leave Contractors Holding the Bag
Sometimes when we are told […]
Roads & Bridges | From Roman Arches to AI
FROM ROMAN ARCHES TO AI
Can Construction Evolve Without Risk?
The construction industry blends old with new. From ancient Roman archways and aqueducts and […]
Roads & Bridges | Caught in the Middle
CAUGHT IN THE MIDDLE
New Mexico bridge case highlights the importance of written agreements for changes and delay compensation
In construction contracting, hope for […]
Roads & Bridges | Wait and It’s Waived
WAIT AND IT’S WAIVED
Roads & Bridges | Supreme Court Ruling on Arbitration Delay
Don’t wait to arbitrate! Progressing too far down the litigation […]
Roads & Bridges | Court Defines When Contractors Can Withdraw Due to Mistakes
BIDDING BLUNDER
Roads & Bridges | Court Defines When Contractors Can Withdraw Due to Mistakes
For over 125 years, the vast majority of jurisdictions […]
FEDERAL CONTRACT TERMINATION OR MODIFICATION
The White House has directed Agency heads to “terminate or modify . . . covered contracts.” With some exceptions, there are […]










