If your Claim includes an item for damages with an amount “TBD,” you could lose the entire Claim.
A Claim is a written demand by a contracting party for payment of a “sum certain” or other relief. F.A.R. 52.233-1(c)
For example, a Contractor agreed to provide facilities maintenance and repair, among other services, at Fr. Meade, Maryland. The Contractor submitted a Claim to the Contracting Officer for several cost items. Among them was an item for “anticipatory lost profits” in an amount “TBD. Although portions of the Claim were for definite amounts, the ASBCA dismissed the entire appeal because at least one part of the Claim was not for a “sum certain.” The part of the Claim for an amount “TBD” tainted the entire Claim.
The Board provided some guidance for Contractors. If a “sum certain” cannot be calculated, then a Contractor should specifically describe:
- How to perform a calculation for a sum certain;
- What information the calculation would be based;
- Where such information exists;
- What the Contractor has done to acquire such information; and
- That, due to no fault of the Contractor, such information is not available.
If you can’t calculate a sum certain or you doubt your explanation, separate the uncertain amount from the rest of your Claim and submit it as a separate claim. At least then, it won’t taint the rest of your Claim.
Roads & Bridges | Maximizing Damage Recovery
MAXIMIZING DAMAGE RECOVERY
Tracking Costs, Avoiding Duplication in Liquidated and Actual Damage Claims
A County and Contractor contracted for construction of a road and […]
Roads & Bridges | Roadwork, Delays and Disputes
ROADWORK, DELAYS, AND DISPUTES
The Subcontract Case In Pecos County, Texas
“Road construction is ubiquitous in our society. . . .” C&C Road […]
Roads & Bridges | Understanding Sovereign Immunity
UNDERSTANDING SOVEREIGN IMMUNITY| Public Contracts and Lessons from Recent Texas Cases
Generally, governmental entities are immune from lawsuits. One exception is contractual. If […]
Roads & Bridges | Indiana Court Upholds Broad ND4D Clause
INDIANA COURT UPHOLDS BROAD ND4D CLAUSE | Ruling Precludes Subcontractor Claims for Delay and Acceleration Damages
This is the story of an Indiana […]
Roads & Bridges | Some Conditions Apply
SOME CONDITIONS APPLY | The scope of insurance policy coverage and what the terms dictate
At some time or another, many have tried […]
Roads & Bridges | Contract Termination
CONTRACT TERMINATION | An unpredictable case teaches hard lessons to each party involved
Court decisions are “opinions.” There are majority and dissenting (disagreeing) […]
Roads & Bridges | Good Faith and Fair Dealing
GOOD FAITH AND FAIR DEALING | How Do You Prove a Party Has Failed to Act Based Upon an Ulterior Motive?
The duty […]
Roads & Bridges | Not Another Notice Story
NOT ANOTHER NOTICE STORY| This Defensive Argument Seems to be on the Rise
AS I CONSIDERED the subject matter for this column, I […]
Roads & Bridges | All According to Plan
ALL ACCORDING TO PLAN | Exact Measurements Go a Long Way
In December 2013, a contractor agreed to replace four bridges for the […]