How often do you get (or give) Halloween treats without the magic words, “Trick or Treat!”?
Many Government Contractors are aware of and careful to include a proper certification of their contract claims to the Federal Government, as required by the Contract Disputes Act. But, they should also expressly request a Contracting Officer’s Final Decision on the claim. Without an express, or at least implied, request the various Boards of Contract Appeals may have no choice but to dismiss a Contractor’s later appeal.
Without a request for a contracting officer’s final decision, claimants may seek treats, but get tricked instead.
Appeal of Andrews Contracting Services, LLC, ASBCA No. 60808 (May 22, 2017).
Maropakis Carpentry, Inc. v. U.S., 609 F.3d 1323 (Fed. Cir. 2010).
Jurisdiction is Power
Not bad power, but the ability of a decision-maker (e.g., court) to decide which side is right (or which is more correct). […]
Roads & Bridges | Defining Labor
DEFINING LABOR | How the Miller Act continues to shape the industry
In the late 1700s, risks of nonpayment caused a shortage of […]
Roads & Bridges | Mediation Melee
MEDIATION MELEE| An arbitration case can be costly
Arbitration can be a bridge over troubled waters. In this crossing, the parties argued over […]
Roads & Bridges | Written Notice
WRITTEN NOTICE | Beware that strict compliance of the contract might be required.
When an owner replaced a contractor for significant safety violations, […]
Roads & Bridges | Mommie Dearest
MOMMY DEAREST | The story of an ESA without a MOM
Nobody enters this world, or a contract, without a mother: There can […]
IIJA | Does Closing a “Giant Loophole” Cost Contractors?
A recent article published by Roads and Bridges magazine reports that the Office of Management and Budget is working to broaden the scope […]
Roads & Bridges | Buy American Plan Gets an Update
BUY AMERICAN PLAN GETS AN UPDATE
The Office of Management and Budget is developing standards to replace the current Buy […]
Roads & Bridges
Where Does the Buck Stop?
WHERE DOES THE BUCK STOP? | A shallow concrete pour leads to an interesting lawsuit
On the desk of President Harry S. Truman […]
Roads & Bridges | Reshaping Agreements
RESHAPING AGREEMENTS | Oral Agreements Must Be Written in Stone
Reuse, reshaping, and/or reapplication of existing materials was the goal in this roadway […]