“Two roads diverged in a wood, and . . .” the Prime Contractor had to take both roads at the same time to the same place.
Problem Example
Subcontractor on project for the U.S. Army Corps of Engineers at Ft. Lee, Virginia, sued Prime Contractor and Surety for nonpayment under the Federal Miller Act. Prime and Surety wanted to pause (stay) the litigation while pursuing arbitration. The Court granted a stay of the litigation for the Prime. The Court denied the stay of the litigation for the Surety because:
- The Surety was not obligated under any written agreement to arbitrate and
- The Surety’s liability under the Miller Act is independent of the Prime’s liability (these two facts are true in most instances).
In other words, even if the Prime owes nothing to the Subcontractor, the Surety could still owe payment to the Subcontractor if the lawsuit was timely filed, the work was done, and the Subcontractor was not already paid. In this case, the Prime had to pay for the Surety’s defense (a typical obligation) in the litigation while simultaneously paying for its own arbitration defense.
Potential Solution(s)
To avoid/reduce this dual-track approach/cost, prime contractors can:
- Seek the surety’s prior written agreement to arbitrate;
- Apply the American Arbitration Association’s Fast Track Procedures if the disputed amount is less than $100,000; or
- Require Alternative Dispute Resolution before any litigation (this will work in the Federal First Circuit (ME, NH, MA, and RI), but may not work in all Federal Courts). (Caution: Requiring arbitration of a Miller Act dispute will not pause the one-year statute of limitations to file a Miller Act lawsuit.)
Roads & Bridges | Connecting the Dots
CONNECTING THE DOTS | Showing Causation in Contracting Cases is Critical
In this asphalt case, the prime contractor agreed to perform a $13 […]
Roads & Bridges | Liquidated Damages
LIQUIDATED DAMAGES | Penalties and What is Unenforceable
Liquidated damages typically flow from delays, but they are not always solidly enforced.
In June 2017, […]
Roads& Bridges | Warranty Provisions
WARRANTY PROVISIONS | Contracts must be interpreted thoroughly to avoid absurd results
You are responsible for things within your control. Be careful if […]
Roads& Bridges | The Agreed Price
THE AGREED PRICE | This case stands as a warning about pay-if-paid clause
History cannot be rewritten and a bad, but legal, […]
Roads& Bridges | Confusing Waters
CONFUSING WATERS | A Supreme Court ruling leaves room for ambiguity
What happens when there may be a “significant nexus” between “adjacent” and/or […]
Roads & Bridges | Authority Defined
AUTHORITY DEFINED | The Law of Agency is Important to Understand
For any project, this Russian proverb is helpful: Doveryay, no proveryay – […]
Jurisdiction is Power
Not bad power, but the ability of a decision-maker (e.g., court) to decide which side is right (or which is more correct). […]
Roads & Bridges | Defining Labor
DEFINING LABOR | How the Miller Act continues to shape the industry
In the late 1700s, risks of nonpayment caused a shortage of […]
Roads & Bridges | Mediation Melee
MEDIATION MELEE| An arbitration case can be costly
Arbitration can be a bridge over troubled waters. In this crossing, the parties argued over […]