“Two roads diverged in a wood, and . . .” the Prime Contractor had to take both roads at the same time to the same place.
Problem Example
Subcontractor on project for the U.S. Army Corps of Engineers at Ft. Lee, Virginia, sued Prime Contractor and Surety for nonpayment under the Federal Miller Act. Prime and Surety wanted to pause (stay) the litigation while pursuing arbitration. The Court granted a stay of the litigation for the Prime. The Court denied the stay of the litigation for the Surety because:
- The Surety was not obligated under any written agreement to arbitrate and
- The Surety’s liability under the Miller Act is independent of the Prime’s liability (these two facts are true in most instances).
In other words, even if the Prime owes nothing to the Subcontractor, the Surety could still owe payment to the Subcontractor if the lawsuit was timely filed, the work was done, and the Subcontractor was not already paid. In this case, the Prime had to pay for the Surety’s defense (a typical obligation) in the litigation while simultaneously paying for its own arbitration defense.
Potential Solution(s)
To avoid/reduce this dual-track approach/cost, prime contractors can:
- Seek the surety’s prior written agreement to arbitrate;
- Apply the American Arbitration Association’s Fast Track Procedures if the disputed amount is less than $100,000; or
- Require Alternative Dispute Resolution before any litigation (this will work in the Federal First Circuit (ME, NH, MA, and RI), but may not work in all Federal Courts). (Caution: Requiring arbitration of a Miller Act dispute will not pause the one-year statute of limitations to file a Miller Act lawsuit.)
Roads & Bridges | Maximizing Damage Recovery
MAXIMIZING DAMAGE RECOVERY
Tracking Costs, Avoiding Duplication in Liquidated and Actual Damage Claims
A County and Contractor contracted for construction of a road and […]
Roads & Bridges | Roadwork, Delays and Disputes
ROADWORK, DELAYS, AND DISPUTES
The Subcontract Case In Pecos County, Texas
“Road construction is ubiquitous in our society. . . .” C&C Road […]
Roads & Bridges | Understanding Sovereign Immunity
UNDERSTANDING SOVEREIGN IMMUNITY| Public Contracts and Lessons from Recent Texas Cases
Generally, governmental entities are immune from lawsuits. One exception is contractual. If […]
Roads & Bridges | Indiana Court Upholds Broad ND4D Clause
INDIANA COURT UPHOLDS BROAD ND4D CLAUSE | Ruling Precludes Subcontractor Claims for Delay and Acceleration Damages
This is the story of an Indiana […]
Roads & Bridges | Some Conditions Apply
SOME CONDITIONS APPLY | The scope of insurance policy coverage and what the terms dictate
At some time or another, many have tried […]
Roads & Bridges | Contract Termination
CONTRACT TERMINATION | An unpredictable case teaches hard lessons to each party involved
Court decisions are “opinions.” There are majority and dissenting (disagreeing) […]
Roads & Bridges | Good Faith and Fair Dealing
GOOD FAITH AND FAIR DEALING | How Do You Prove a Party Has Failed to Act Based Upon an Ulterior Motive?
The duty […]
Roads & Bridges | Not Another Notice Story
NOT ANOTHER NOTICE STORY| This Defensive Argument Seems to be on the Rise
AS I CONSIDERED the subject matter for this column, I […]
Roads & Bridges | All According to Plan
ALL ACCORDING TO PLAN | Exact Measurements Go a Long Way
In December 2013, a contractor agreed to replace four bridges for the […]